Submitter

Director
Robert Peterson - Director - Public Works
Report By
Janet Walker - CIVIL ENGINEER - 259-8383
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
"Various County Road Overlays and One County Road Slurry Seal Project" RDS 08-07 - Notice of Completion
Special Instruction

 

Recommendation

Director of Public Works requests acceptance of the work as complete and authorization for the Chair to sign and Clerk of the Board to file a Notice of Completion with the Clerk/Recorder for Contract No. RDS 08-07, "Various County Road Overlays and One County Road Slurry Seal Project".

Summary

On July 15, 2008, the Board of Supervisors awarded the contract "Various County Road Overlays and One County Road Slurry Seal Project"  RDS 08-07  to Vintage Paving Company, Inc. of Winters, CA for its low base bid of bid of $1,227,741.  The work is now complete and the Director of Public Works requests approval to file a Notice of Completion.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification

Notice of Completion must be filed in order to complete the project.

Is the General Fund Affected
Yes
Future Fiscal Impact?

None

Consequences if not approved

Notice of Completion cannot be filed.

Additional Information

Total construction costs are $1,331,575, which includes the contract amount of $1,227,741 and Change Orders of $103,834 for additional asphalt, slurry seal and striping.  Specifically, construction costs for Silverado Trail are $703,800; $464,524 for Petrified Forrest Road; and $163,252 for West Pueblo and Vista Manor.  The total project cost is estimated to be $1,398,950, which includes project management, design, construction management and inspection, and materials testing.   

Funding of this project is provided in part by Proposition 1B funds in the amount of $1,160,160, which have already been received in the amounts of $600,000 for Silverado Trail, $360,160 for Petrified Forest Road, and $200,000 for West Pueblo.  The City of Napa will be billed $21,271 for work performed on its streets in West Pueblo.  The remaining funds are provided by Road Fund Balance.

The General Fund has provided a contribution of $2.8 million to the Roads budget in the FY 2008-09 budget.  Therefore any project that is not 100% financed with other revenue sources is considered to have a General Fund impact. 

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

Background

On March 18, 2008 the Board adopted a resolution approving specific projects to be constructed utilizing the Highway Safety, Traffic Reduction, Air Quality, and Port Security Bond Act of 2006 (Proposition 1B) revenue.  Staff had processed a request with the State Controller to release the Proposition 1B funds to the County of Napa.  The County is in receipt of this funding.   

On June 3, 2008, the Board of Supervisors approved plans and specifications for the "Various County Road Overlays and One County Road Slurry Seal Project"  RDS 08-07.  Bids were solicited and on July 15, 2008 the contract was awarded to Vintage Paving Company, Inc. of Winters, CA.           

This project was comprised of 3 locations: Siverado Trail from Stag's Leap to Yountville Crossroad was overlaid.  Petrified Forest Road from its intersection with Franz Valley Road to the County Line was also overlaid.  A slurry seal was installed in the West Pueblo and Vista Manor subdivisions.  City segments in the West Pueblo subdivision were included in the work and the County and City have an agreement which will reimburse the County for that work.  The project is now complete, and the Notice of Completion must be filed.