Total construction costs are $1,331,575, which includes the contract amount of $1,227,741 and Change Orders of $103,834 for additional asphalt, slurry seal and striping. Specifically, construction costs for Silverado Trail are $703,800; $464,524 for Petrified Forrest Road; and $163,252 for West Pueblo and Vista Manor. The total project cost is estimated to be $1,398,950, which includes project management, design, construction management and inspection, and materials testing.
Funding of this project is provided in part by Proposition 1B funds in the amount of $1,160,160, which have already been received in the amounts of $600,000 for Silverado Trail, $360,160 for Petrified Forest Road, and $200,000 for West Pueblo. The City of Napa will be billed $21,271 for work performed on its streets in West Pueblo. The remaining funds are provided by Road Fund Balance.
The General Fund has provided a contribution of $2.8 million to the Roads budget in the FY 2008-09 budget. Therefore any project that is not 100% financed with other revenue sources is considered to have a General Fund impact.