Amendment No. 1 to Napa County Agreement No. 7323 with Phillip Williams & Associates - Napa River Rutherford Reach Restoration Project, Reach 4 and Reach 8 Design
Special Instruction
Please return 2 copies of the signed amendment to John Vicencio in Public Works
Recommendation
Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 1 to Agreement No. 7323 with Phillip Williams & Associates increasing the amount by $206,100 for a new maximum of $607,200 extending the term of the Agreement through June 30, 2011 with an automatic extension provision and amending the scope to include the additional services of completing final plans, specifications, and permit applications, and providing construction administration support services for restoration of Reach 4 and a portion of Reach 8 of the Rutherford Dust Restoration Project.
Summary
The Rutherford Dust Society (RDS), the County of Napa, the Flood District, and Napa County Resource Conservation District (RCD) entered into a Memorandum of Understanding (MOU) in March 2005 defining roles and responsibilities to accomplish a plan for restoration and management of a 4.5 mile stretch of the Napa River in the Rutherford appellation. The County's role in the MOU is design and construction of the project consisting of 9 reaches. Construction of Phase 1 of the project, encompassing Reaches 1 and 2, began in 2009 and was completed in summer 2010. Construction of Phase 2, which encompassed Reach 3 of the river, was also completed in summer 2010.
A Professional Service Agreement with Phillip Williams & Associates (PWA) for Reach 4 design was approved by the Board on November 10, 2009. Reach 4 design is currently underway and funding for construction is partially supported by a grant from the State of California Department of Parks and Recreation Habitat Conservation Fund, matched with Measure A funds. An additional grant application from the State Water Resources Control Board is also under review by the State. Additional services are now required of PWA to address regulatory agency permit conditions for Reach 4 and also to include a portion of Reach 8 in the plans and specifications for the next construction phase. Reach 8 is the next priority following Reach 4 and based on critical erosion issues that have been identified on the Sequoia Grove property. The Board approved funding for the design of this portion of Reach 8 in the Fiscal Year 2010-2011 budget. PWA is not a local vendor.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Amendment of the agreement is needed to address additional services required to complete the Reach 4 design based on comments from regulatory agencies and also to include the design for repair of a critical area of erosion into the next construction contract. By designing Reach 4 and a portion of Reach 8, these portions of the project will be "shovel-ready" for construction grant opportunities.
Is the General Fund Affected
No
Future Fiscal Impact?
None.
Consequences if not approved
Potential loss of landowner involvement, investment in conceptual and preliminary design as well as further degradation of the Napa River can occur. River restoration and flood control efforts along the Napa River in the Rutherford area cannot proceed further.
Impact
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable to this action.
Background
In 2009, staff interviewed and reviewed proposals from 3 consulting firms for the final design of the restoration and management of a 4.5 mile stretch of the Napa River in the Rutherford Appellation. Phillip Williams & Associates was chosen as the most qualified firm based on its previous experience with the conceptual design of this project and experience with other similar projects. Individual design contracts by river reach have been approved as funding opportunities for construction have been identified for those reaches.
The original Professional Service Agreement with Phillip Williams & Associates (PWA) for Reach 4 design was approved by the Board on November 10, 2009. Additional services are now required of PWA to address regulatory agency permit conditions for Reach 4 and also to include a portion of Reach 8 in the plans and specifications for the next construction phase. Reach 8 is the next priority following Reach 4 and based on critical erosion issues that have been identified on the Sequoia Grove property. The Board approved funding for the design of this portion of Reach 8 in the FY 2010-2011 budget. Further design in Reach 8, outside of the Sequoia Grove area, will be addressed in the budget for next fiscal year.
Reach 4 is funded by Measure A funding as provided by Amendment 12 to Measure A Funding Agreement 4202 with the Napa County Flood Protection and Watershed Improvement Authority, as approved by the Board September 15, 2009. Funding for the Sequoia Grove area of Reach 8 was provided by Amendment 13 to Agreement 4202, as approved by the Board June 29, 2010. The goal of completing the design for Reach 4 and Reach 8 is to be able to have plans ready for construction to make the project more competitive for future implementation grant funding opportunities.
At this time it is planned that construction will commence in Reach 4 in summer 2011. Pending award of additional grant funds, completion of construction in Reach 4 and Reach 8 would likely be in 2012. Reach 4 construction is partially supported by a grant from the State of California Department of Parks and Recreation Habitat Conservation Fund, matched with Measure A funds. An additional grant application from the State Water Resources Control Board is also under review by the State.
Approval of Amendment No. 1 to the Agreement with PWA is requested at this time. Although PWA is not a local vendor, staff recommends that the additional required services be performed by them as the chosen designer of the project through a request for qualifications process and because of the specialized expertise that they bring to the project.