Appoval of Plans and Specifications and authorization to solicit bids - Napa County Airport General Aviation Apron Rehabilitation PW 11-12
Recommendation
Director of Public Works requests approval of plans and specifications for the "Napa County Airport General Aviation Apron Rehabilitation - Phase 2A Project," PW 11-12, authorization to advertise for sealed bids and opening of the bids at a time, date and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code.
Summary
An Airport Pavement Management System (APMS) report was prepared in 2010 in accordance with Federal Aviation Administration (FAA) guidelines to provide an updated visual condition survey of all airfield pavements, pavement condition rating for each pavement area, and specific recommendations on rehabilitation and maintenance needs for all airfield pavement.
The APMS recommends rehabilitation of the airport apron surface and drainage due to prominent cracking caused by age and weathering. The 'apron' is the part of the airport where aircraft are parked, loaded and unloaded, refueled, and boarded. The first section to be rehabilitated is the area directly in front of the hangars, the southernmost end of the apron. Subsequent rehabilitation projects will be phased progressing toward the northern end of the apron.
The FAA has approved Napa County to solicit bids for the project since this is a project that they will fund this year. Once bids are opened staff will formally request the FAA to fund the project prior to requesting Board award of a construction contract. Staff anticipates beginning construction in the Summer of 2011.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
This project is required to maintain existing airport facilities and enhance services provided by the Airport to its customers.
Is the General Fund Affected
No
Future Fiscal Impact?
Construction is expected to be completed in the Fiscal Year 2011-2012.
Consequences if not approved
The General Aviation Apron will remain in its current condition, and there will be no benefit from funds expended for design of the apron rehabilitation.
Additional Information
The FAA is expected to allocate $2,090,000 for construction of the rehabilitation of the main apron. State Department of Transportation funding for this project will then be $52,800, with a local Airport Enterprise Fund match of $57,200 in the approved budget.
Impact
Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]
Background
The FAA reviews the projected 5-year Airport Capital Improvement Program (ACIP) once a year and after review notifies the Airport which project(s) will be included in the FAA budget for the next fiscal year. The AIP funded projects are based on the approved Airport Layout Plan (ALP) and Master Plan, airport needs, and projects that have been given environmental clearances.
In "Phase 1" of the apron rehabilitation, a preliminary design of the apron was done, and based on this preliminary design the rehabilitation has been divided into 4 sections (Phase 2A, 2B, 2C, and 3) and will be done incrementally as funding becomes available. The rehabilitation will remove the existing pavement, rework the aggregate base and treat with lime as needed to increase the base strength, realign the drainage system, install new surface, and replace all striping.
Plans and Specifications for the initial segment Phase 2A are complete and have environmental clearance. After bid opening, staff will return to the Board for award of the contract. The remaining segments will be designed and constructed at later dates as additional funding becomes available.