Amendment No. 2 to Agreement 7174 with Quincy Engineering, Inc. for Final Design of the "Dry Creek Road Repair Project," RDS 07-18
Recommendation
Director of Public Works requests approval of and authorization for the Chairman to sign Amendment No. 2 to Agreement No. 7174 with Quincy Engineering, Inc. increasing the amount by $33,797 for a new maximum of $124,452 and amending the scope of work to include completing final plans and specifications, and providing construction administration support services for the "Dry Creek Road Repair Project," RDS 07-18.
Summary
On January 27, 2009 the Board authorized a Professional Services Agreement with Quincy Engineering, Inc. for the purpose of providing design services and construction support for the "Dry Creek Road Repair Project," RDS 07-18. On April 13, 2010 the Board authorized Amendment No. 1 which addressed additional design requirements due to environmental considerations and construction support for the project.
Work to be performed under Amendment No. 2 will revise the current soldier pile retaining wall design to incorporate rock slope protection along the base of the construction limits and into the stream channel. This design revision is required by the regulatory agencies and must be incorporated into the plans to gain environmental approval.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Quincy Engineering, Inc. is under contract for the design of the "Dry Creek Road Repair Project," PW 07-18. Additional design efforts are needed due to regulatory agency requirements.
Is the General Fund Affected
No
Future Fiscal Impact?
Project expenses, including construction costs, will continue to be incurred into Fiscal Year 2011/2012.
Consequences if not approved
Flood repairs will not be completed.
Additional Information
The Federal Emergency Management Agency (FEMA) has committed to obligating funding when environmental clearance is obtained. A total of 75% of the funding is to be provided by Federal FEMA funds and the remaining 25% by State of California Emergency Management Agency (CalEMA) funds.
Impact
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable to this action.
Background
On September 9, 2008 a Request For Qualifications was issued for design services for the repair of two of the five remaining damaged sites from the flood of 2005-2006, one of them being Dry Creek Road. Staff reviewed the statements of qualifications, interviewed proposers, and established a ranking of the proposers based on their qualifications for flood repair projects. Quincy Engineering, Inc. was selected to provide design services and construction support for the "Dry Creek Road Repair Project," RDS 07-18. The Board authorized a Professional Services Agreement with Quincy Engineering, Inc., Contract No.7174, on January 27, 2009.
As work progressed on the project it was determined that environmental constraints had been identified and required modification to the design. The Board authorized Amendment No.1 to the contract with Quincy on April 13, 2010 to provide additional engineering work to complete the design while meeting environmental constraints. Recent comments from the regulatory environmental agencies have led to the need for additional design efforts.
Work to be performed under Amendment No. 2 will revise the current soldier pile retaining wall design to incorporate rock slope protection along the base of the construction limits and into the stream channel. This design revision is required by regulatory agencies and must be incorporated into the plans to gain environmental approval. FEMA has committed to obligating funding when environmental clearance is obtained. Funding provided is 75% Federal FEMA funds and 25% State CalEMA funds. When the obligation notice is received, staff will bring the plans and specifications to the Board for approval.
Staff is targeting construction of this project for the Fall of 2011 pending environmental clearance.