Submitter

Director
LENARD VARE - Director - Corrections
Report By
Bret Prebula - STAFF SERVICES MANAGER - 707-253-4342
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Public Safety
Subject
Authorization to approve a budget transfer and establishing a fixed asset.

Recommendation

Director of Corrections requests approval of Budget Transfer No. COR003 increasing appropriations in the amount of $8,900 with offsetting revenues from the Corrections budget and establishment of a fixed asset in the amount of $8,900 for the purchase of two ground water pumps and a duplex control panel.  (4/5 vote required)

Summary

On February 9, 2011,  two ground water pumps in the jail failed. These pumps were originally installed around 1988. One pump failed because the pump mechanism seized up, the other failed because it tripped the electrical overload. The failures allowed excess water to remain under the building and created enough pressure to bulge the tile in the kitchen. Subsequently, staff is working on repairing the damaged tile in the kitchen and was able to repair one pump, but this pump is running at the maximum allowable amperage and could fail at any time. In order to avoid any further damage and/or the failure of the one repaired pump staff invoked the emergency purchasing provision of the County's Purchasing Policy, purchasing two replacement pumps and a new control panel. 

The purchase and installation of the two ground water pumps and control panel will allow the Department to repair the system to proper working order. Due to the timing of the Board schedule and delivery lead time for the above described items staff was did not have ample time to receive Board approval before purchasing the fixed asset. Due to the above mentioned factors the Department is requesting the Board approve the budget transfer and establishment of a fixed asset to complete the transaction and release payment to the vendor.

 

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?

Although the item was not budgeted in the Department's FY10-11 budget, the Department can absorb the cost of the item.

Is the activity Mandatory or Discretionary
Mandatory
Is the General Fund Affected
No
Future Fiscal Impact?
Currently, for the purchase of this equipment there is no impact past this fiscal year. Depending on the life cycle of the equipment there may be additional future fiscal year costs associated  with the replacement of the control panel and ground water pumps. The previous equipment lasted over 20 years and baring no unforeseen damage or failures staff does not believe there will be a need to replace this control panel and/or ground water pumps within the near future.
Consequences if not approved
Since this piece of equipment was deemed an emergency purchase the item has already been ordered. If not approved, the department would not be able to pay the vendor thus the ground water pumps and control panel would have to be returned to the vendor. This would cause a major hardship as staff would not be able to effectively cycle the water out of the basement and thus would have to rely on the one repaired pump for the entire system. If this pump failed water would settle under the building and the pressure would most likely cause the tile to bulge and potentially break in the kitchen. There would be no replacement pump and further damage to the facility would occur.  

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

Background

On February 9, 2011, two ground water pumps failed. These pumps were original equipment installed around 1988. The failure of these pumps allowed excess ground water to remain under the building and created enough pressure to bulge the tile in the kitchen (see attached photo). The Department was able to repair one of the pumps but the pump is running at the maximum allowable amperage, thus it could fail at any time. In order to correctly address the problem and to mitigate any future issues the Department used the emergency purchase provision to purchase two pumps and a new control panel. The new control panel was required because the new pumps were not compatible with the current control panel. Since the failed pumps were from 1988 any new equipment installed would require a new control panel as the previous equipment is obsolete and past its useful life.

Normally, this would require the Department coming to the Board of Supervisors to request approval of a budget transfer and establishment of a fixed asset before the item could be purchased. Due to the urgent nature of the problem staff believed the purchase of the two ground water pumps and control panel fell into the emergency purchase provision of the County's Purchasing Policy.

After consulting with the Purchasing Manager it was deemed the purchase would fall under section 4-3 of the County's Purchasing Policy allowing for the emergency purchase. Subsequently the item was ordered. In order to complete the transaction the department is requesting the Board approve a budget transfer and establishment of a fixed asset. If approved, the Department has adequate budget to pay the vendor and complete the transaction.