Submitter

Director
Ridenhour, Don - Director - Public Works
Report By
Anthony Morales - Associate Engineer - (707) 259-8373
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
4800 Redwood Road Repair Project, RDS 07-16 - Approval of Plans and Specifications and Authorization to Advertise for bids

Recommendation

Director of Public Works requests approval of plans and specifications for the “4800 Redwood Road Repair Project,” PW 07-16, authorization to advertise for sealed bids and opening of the bids at a time, date and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code.

Summary

This project provides for road repairs in the vicinity of the 4800 block of Redwood Road, repairing damage sustained in two separate declared emergencies: the December 2005 and March 2006 flood events.   Plans and specifications are complete and FEMA has given environmental clearance for construction. 

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Repairs are necessary to this segment of the road system which sustained damage in the floods of 2005 -2006.
Is the General Fund Affected
No
Future Fiscal Impact?
Construction will occur in the Fall of Fiscal Year 2011-2012.
Consequences if not approved
Flood repairs to this road will not be completed.
Additional Information
Because the damage resulted from two separate disaster events, the FEMA obligation is for two separate, distinct ‘sites’ and repairs to the two ‘sites’ must be tracked separately and reimbursement applied for separately. Bid documents have been crafted in a manner which facilitates this tracking. Staff worked with CalEMA and FEMA to develop the format of the bid documents for the tracking.

The engineer's construction cost estimate is $510,000 for Site 1 and $230,000 for Site 2, for a total of $740,000. FEMA obligation for the sites is $956,373 and $445,176 respectively for a total of $1,401,549. This includes funding for the construction and contingency, design consultant, project management, and construction inspection and materials testing. 75% of the cost is funded by FEMA and 25% by State of California Emergency Management Agency (CalEMA).

Impact

ENVIRONMENTAL DETERMINATION: This project is subject to both the California Environmental Quality Act (CEQA) process and the National Environmental Policy Act (NEPA) process. The CEQA and NEPA determinations are as follows:

Categorical Exemption Class 2 : It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 2 (“Replacement or Reconstruction”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15302.]

Categorical Exclusion : an action which does not have a significant environmental effect and is excluded from the requirement to prepare an Environmental Assessment or Environmental Impact Statement. The project is Categorically Excluded from the National Environmental Policy Act under 44 CFR 10.8(d): repair, restore, retrofit, upgrade to current codes and standards, or replace a facility.

Background

This project provides for road repairs in the vicinity of the 4800 block of Redwood Road, repairing damage sustained in two separate declared emergencies, the December 2005 and March 2006 flood events.  For FEMA tracking purposes these are defined as 'Site1' and 'Site 2'.   The 'sites' are contiguous, in reality constituting one repair site.  Solicitation of bids for repairs at Site 1 and Site 2 will be consolidated into one solicitation and one contract for construction, with activities and invoicing separated to track the two repairs as FEMA requires.  FEMA, through CalEMA, has approved the extended completion date based on the extenuating circumstances of known environmental constraints, such as critical wildlife habitat disturbances during construction involving the red-legged frog and the spotted owl. Issues regarding these environmental constraints have been resolved, but have limited the construction window to a period between August 15 and October 15 on any given calendar year.  All environmental clearance has been obtained.

Flood repairs were constructed in their prioritized order, and this repair is one of the few last remaining repairs of flood damage.

Attachments

There are no attachments to this item