Phillip Miller - DEP DIR PW-FLOOD CTRL & WATER - 707-259-8620
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
Amendment No. 1 to Agreement 7457 with Howard Siegel
Special Instruction
Recommendation
Director of Public Works requests approval of and authorization for the Chairman to sign Amendment No. 1 to Agreement 7457 with Howard Siegel extending the term through June 30, 2012 with no change to the scope of work.
Summary
Director of Public Works is requesting approval of an amendment to the professional services agreement approved by the Board on August 10, 2010 to augment staff and provide services critical to advancing the Milliken-Sarco-Tulocay (MST) Phase 1 recycled water project in the groundwater deficient area. Significant progress has been made toward design and financing of the project that will provide addition water resources to the MST area. Additional staff resources are needed to coordinate with state and local agencies and the community to implement the financing mechanism for the construction of recycled water facilities. Staff has been supplemented by Howard Siegel. He is a local vendor and brings local knowledge and the skill set to work and coordinate with other agencies, special groups, and the community.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The Public Works Department has made great progress in advancing the MST Phase 1 Recycled Water Project to bring recycled water to the MST area and continues to need supplemental staff resources to work with other agencies and develop financing mechanisms to pay for the construction of the project.
Is the General Fund Affected
No
Future Fiscal Impact?
It is not anticipated that consulting services will be necessary past June 30, 2012.
Consequences if not approved
If the amendment is not approved it will be very difficult to successfully move the MST Phase 1 Recycled Water project along with the staff resources available in the Public Works Department.
Impact
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.
Background
On May 24, 2011, the Board approved Amendment #15 to the Napa County Measure A Funding Agreement No. 4202 providing an additional $614,000 to fund MST project tasks including participation in the North Bay Water Reuse Authority and coordinating with other agencies such as the Napa Sanitation District and State Water Resources Control Board, and the community to advance efforts to implement the MST Phase 1 Recycled Water Project. Due to other water resource tasks in the Public Works Department, supplemental professional services are still needed to move recycled water project toward construction and further efforts to bring additional water resources to the MST groundwater deficient area. Howard Siegel is a local contractor and brings local knowledge and the skill set to work with other agencies and to coordinate with agencies, special groups, and the community to implement funding mechanisms to construct the facilities.
The amendment before the Board today will continue to provide a dedicated person to augment staff that can keep the MST project on track and moving toward construction. The Napa Sanitation District is constructing a recycled water pipeline through Napa State Hospital to Imola Avenue. A half-mile long extension to Skyline Park is out to bid. Design of the MST Phase 1 Recycled Project is essentially complete. Provided the funding can be developed, County staff anticipate beginning construction of the project in 2012 to extend recycled water pipelines into the MST area and it will be critical to finalize financial mechanisms to present to the potential users and the community. The description of services to be provided are as follows:
Planning, organizing, and coordinating water resources planning activities to facilitate the development and construction of recycled water facilities or other sources of water to serve the Milliken-Sarco-Tulocay groundwater deficient area;
Coordinate efforts to develop a financing mechanism to pay for recycled water facilities with private interests and the County’s assessment district engineer;
Lead, organize, and facilitate meetings with community residents, technical advisory groups, design engineers, elected officials and staff from participating agencies including but not limited to the County, City of Napa, Napa Sanitation District, and the North Bay Water Reuse Authority;
Assist with submittal and processing of a State Revolving Fund loan application with the State Water Resources Control Board to fund initial construction of the project;
Assist with establishment of a Community Facilities District to provide the needed revenue stream;
Assist in identifying additional potential recycled water users;
Assist in the search for grants, loans, and/or other funding opportunities for expansion of recycled water facilities and manage groundwater; and
Provide other services as needed to further the County’s efforts to expand the use of recycled water or other sources of water to serve areas of the County with deficient or limited groundwater resources.