Summary

Building fee revenues rebounded in the first quarter of FY2011/2012, tentatively signalling improvements to the local economy and allowing the Conservation, Development and Planning Department to defer further cost saving measures.  With the increased workload (as evidenced by the value of the construction), staff is seeking Board of Supervisors direction on three fee policy questions:  possible amendment to the County policy on fee waivers for fully fee-supported activities; possible amendment to the solar energy installation fees to ensure full cost recovery; and possible adjustments to reflect changes in the cost of living.  More explanation regarding each of these questions is provided in the Background section, below.  If the Board of Supervisor directs staff to pursue one or more of these policy changes, staff would undertake a full analysis for consideration by the Board in the spring of 2012 and implementation of any changes (if adopted) in FY2012/2013.  Staff's analysis would include coordinating with other permitting departments to assess possible fee adjustments warranted in their areas. 

PROCEDURAL REQUIREMENTS

  1. Staff report;
  2. Public comment;
  3. Board discussion 

Fiscal Impact

Is there a Fiscal Impact?
No

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

Background

The Building Division of the Conservation, Development & Planning Department is responsible for processing building permit applications, including plan reviews and inspections, and also routes applications to other agencies for their review and sign-off.  The Division is fully fee-supported, and does not receive any General Fund support.  The Division charges fees on a valuation basis (i.e. based on the value of the construction project being permitted) and its fees have been set to cover the cost of performing necessary plan reviews and inspections, including administration and overhead. 

When the Building Division fees were last adjusted in 2009 and 2010, they were set assuming there would be good times and bad.  In good times, the fees collected would cover the Building Division’s costs and contribute a surplus to the Building Fund for use in completing pending work in subsequent fiscal years.  In bad times, the Building Fund would be drawn down to cover some of the Building Division’s costs.  This is precisely what has happened in the current economic downturn, except the “bad times” were more severe and longer in duration than ever anticipated.  As a result, the Building Division has had to cut its expenses by eliminating (or not filling) staff positions and instituting voluntary furloughs.  Further cost savings -- potentially affecting plan review times and other customer services -- would have been necessary at the end of FY11/12 if revenues had not started to increase in the first quarter.

With the economy starting to show signs of recovery, there are three policy questions related to building permit fees and the Building Fund that staff would like Board direction on.  These questions are timely due to the passage of Proposition 26 in 2010, which essentially precludes the County from using fees collected from applicants to achieve policy objectives unrelated to the services being provided. While Proposition 26 applies to fees prospectively, building fees related to solar have been supplemented by the Building Fund for many years. Since the Building Fund is an enterprise account and the Building Division is entirely fee supported, it’s essential that the building fees only be used to support Building Division activities.

Would the Board like to reconsider the County’s fee waiver policy for fully fee-supported activities?

The County’s fee waiver policy is contained in Section 10.020 of the County’s Fee Policy and Procedures, and applies to all fee departments (e.g. Building, Planning/Conservation, Fire, Public Works, Environmental Management, Ag Commissioner).  The Policy allows department heads and the CEO to waive fees if three findings can be made:

  1. the waiver of the fee will advance a public policy; and
  2. the waiver of the fee is in the public interest and will promote a public benefit; and
  3. the applicant is a non-profit organization. 

(There is one additional finding required for temporary event fee waivers -- i.e. that a percentage of the proceeds will be donated for the public benefit of the citizens of Napa County -- and temporary event fee waivers are so common that the County has created a special fee [$156.62] for non-profit events where the standard fees are waived.  If the Board would like to modify the overall fee waiver policy, staff would like confirmation that the Board would like to retain this practice.)

Historically, departments have interpreted the fee waiver policy generously and non-profit applicants have been able to achieve fee reductions/waivers on building permits, use permits, and other applications.  These reductions/waivers and the policy as a whole are potentially problematic in departments or divisions which do not receive general fund support (like the Building Division), since fee waivers are essentially subsidized by other permit applicants.  This issue could be addressed by limiting the fee waiver policy to departments or divisions that receive general fund support, and staff would like Board direction to revise the fee waiver policy in this way and to make any other necessary adjustments to the longstanding criteria and approval process.  It should be noted that in many other counties, the Board of Supervisors and not the staff is responsible for reviewing fee waiver requests. 

Would the Board like to institute an annual fee adjustment for cost of living/inflation?

Periodically, the County retains consultants to perform a comprehensive analysis and recommend adjustments to user fees that are charged to applicants.  When the recommended fee increases are large, the Board has often phased them in over a several year period.  However the County has never adopted a policy that would automatically adjust the fees based on changes in consumer prices or the cost of living.  Since building fees are based on valuation, changes in consumer prices are inherent in the fee structure already, although the cost of doing business (salaries and benefits, A87, ITS and liability insurance charges) go up each year and are not reflected.  Building fees have not been formally reviewed since 2009 and given the new Union agreement and anticipated salary and benefit cost increases over the next few years, it may be timely to review the current fee structure and analyze options for building in cost of living adjustments. Staff would like Board direction to analyze needed adjustments to the current fees and to work with County Counsel to consider ways to adjust the fees regularly in the future. This is not a commitment to increase fees, staff would return to the Board with the results of the analysis and any resulting recommendation to the fee structure.

Would the Board like to reconsider building permit fees for solar energy installations?

In October 2006, the Board of Supervisors approved a decrease in the building permit fees charged for solar energy installations. As a result, these projects are now charged lower fees than other projects of similar value, and other building permit applicants are essentially subsidizing time that’s spent on plan reviews and inspections related to solar energy installations (estimated at $84,000 in FY2010/11).    

Staff would like Board direction to analyze needed adjustments to the current fee structure to bring the fees for solar energy installations in line with the cost of processing the applications.  Rather than charging standard building fees, staff is hoping the analysis will support use of the methodology promulgated by the Sierra Club and adopted by the City of Napa.  Under that methodology, there a flat fee that is adjusted upward for more complex installations.  (See the Sierra Club Study attached.) The Board should be aware that directions to analyze or change other fees may trigger the need to automatically increase solar fees to cover costs per Proposition 26.