Submitter

Director
Steven Lederer - Director of Public Works - Public Works
Report By
Zandra Massari - Engineering Aide - 253-4352
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
Napa Library Acoustics & Lighting Retrofit Project - Approval of Plans and Specifications and Authorization to Advertise

Recommendation

Director of Public Works requests approval of plans and specifications for the “Napa Library Acoustics & Lighting Retrofit Project,” PW 11-32, authorization to advertise for sealed bids and opening of the bids at a time, date and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code.

Summary

The Napa Main Library is in need of acoustical wall and ceiling treatments as well as an energy efficient lighting retrofit that is environmentally friendly and will provide long term cost savings to the County.  Plans and Specifications are ready for Board approval and authorization for bid solicitation.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The acoustic wall and ceiling treatments will dampen sounds in this concrete building which currently seems to magnify sounds from its hard surfaces.  A retrofit of the existing lighting will result in cost savings on the electric bills. 
Is the General Fund Affected
No
Future Fiscal Impact?

Construction completion is targeted prior to the end of the fiscal year 2012/2013.

Consequences if not approved
Sound levels in the Library will remain high, and the County will not enjoy the benefit of lower electric bills from the lighting retrofit.
Additional Information
With the estimated cost for the construction at $197,500 being larger than the currently budgeted funding of $64,000, staff will be recommending a budget transfer once bids are opened and staff returns to the Board for the award of a construction contract to the low bidder.  

The project will be utilizing the Pacific Gas & Electric (PG&E) program "On Bill Financing".  This is a 0% loan which is paid back through being invoiced monthly for what had been the historical monthly average, with the savings in electricity charges applied toward the loan principal.   Payback time is estimated to be 5 years.  The exact time will be verified after bids are received and the construction contract amount is forwarded to PG&E. 

Impact

Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]

Background

The Napa Main Library, located at 580 Coombs Street in downtown Napa is the cornerstone for the Napa County Library (NCL) system.  On average, the Napa Main Library receives 1,800+ visitors a day that utilize all aspects of the programs and services offered by NCL.  The Napa Main Library serves the vast majority of the Library users within the system.                            

The control of sound in a library setting is important to patrons' ability to benefit from use of the facility. Patrons come to the library for a variety of reasons; quiet study, find materials, ask a question or enjoy a program. These uses can have a variety of sound levels. While there is an expectation that the library will be quiet, that is not always the case depending upon what activity is taking place. Creating areas in the library that provide for different sound levels and designing the library so sound doesn’t travel from one area to another, enables different functions and uses to occur in the library.                    

Adequate lighting is of the utmost importance in a library setting. Patrons who are reading and using the computers need the proper lighting to avoid eye strain.                             

The proposed project will consist of installing acoustical wall panels and ceiling tiles to absorb sound, and retrofitting lights to more efficient models than are currently in place.   Requests for Qualifications were released separately for both acoustics and lighting consultants.   Environmental Science Associates (ESA) provided architectural acoustics measurement and analyses, and developed treatment recommendations for several individual spaces within the library.  The Lighting Wizard provided services for the lighting, specifying the lights and preparing the light audit necessary for PG&E's On Bill Financing.   With the estimated cost for the construction at $197,500, larger than the currently budgeted funding of $64,000 from the Library fund balance, staff will be recommending a budget transfer once bids are opened and staff returns to the Board for the award of a construction contract to the low bidder.                       

To encourage local vendors, staff will publish a Notice to Contractors in the Napa Valley Register, outreach to the local builders exchange, outreach to local contractors, and post the Invitation for Bid on the County's website.  Once a construction contract is awarded staff will notify the Workforce Investment Board (WIB) of the project and will require the Contractor to contact the WIB so that they can advise the WIB of any hiring needs.