Subject
Napa County Jail Sewer Repairs- Notice of Completion
Special Instruction
Please return to Ginny Leija, Public Works

Recommendation

Director of Public Works requests acceptance of the work as complete and authorization for the Chairman to sign and Clerk of the Board to file a Notice of Completion with the Clerk/Recorder for Contract No. PW 13-30, "Napa County Jail Sewer Repairs."

Summary

On January 16, 2013, the Napa County Director of Public Works, under the Uniform Public Construction Cost Accounting Act authority granted by the Board, awarded Contract No. PW 13-30 "Napa County Jail Sewer Repairs" to Bell Products, from Napa, California for its bid of $12,000.  The work is now complete and the Director of Public Works requests approval to file a Notice of Completion.

Fiscal Impact

Is there a Fiscal Impact?
No

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

Background

On January 7, 2013 the Director of Public Works awarded the construction contract to Bell Projects from Napa for a total of $12,000.  Construction for the project began on February 4, 2013 for excavation of asphalt and concrete and existing sewer piping, installation of new sewer lines and clean-outs, replacement of asphalt and concrete and re-striping of parking spaces.  Construction was completed on February 6, 2013 and the Notice of Completion must be filed. The estimated final cost for this project is $13,000 which includes construction, project management, design engineering, construction management, inspection services, and administrative costs.