Subject
Agreement with Napa Sanitation District for the Construction, Operation and Maintenance of the MST Recycled Water Pipeline

Recommendation

Director of Public Works requests the following actions related to the Milliken-Sarco-Tulocay (MST) Recycled Water Project:

  1. Approval and authorization for the Chairman to sign an Agreement between Napa Sanitation District (NSD) and County of Napa for the construction, operation, and maintenance of a recycled water project in the MST area for a maximum amount of $9,859,000, contingent upon receipt of a funding agreement from the State Water Resources Control Board for a State Revolving Fund loan.  Approval is also requested to share dues costs with North Bay Water Resources Agency (NBWRA) in an estimated amount of $161,086 for the next three fiscal years;
  2. Approval and authorization for the Chairman to sign Amendment No. 6 to Agreement 7350 with NSD in the amount of $131,000 for a new maximum of $2,798,250;
  3. Authorization for staff to direct bill Community Facility District (CFD) members for the Fiscal Year 2013-2014 assessments in the amount of $601,465;
  4. Approval of Budget Transfer No. DPW012 appropriating $145,000 in the Capital Improvement Program 05001 budget with offsetting revenues from State Revolving Funds for project expenses (4/5 vote required); and
  5. Authorization for the Auditor-Controller to create Fund 2870, Division 28700 - Community Facility District (CFD) MST, and approval of Budget Transfer No. DPW013 in the amount of $12,500 with offsetting revenue from the direct billing assessments for administration costs incurred through June 30, 2014. (4/5 vote required)

Summary

The MST basin east of the City of Napa has been designated as a groundwater-deficient area for over 15 years. The County, in partnership with Napa Sanitation District (NSD), has been participating in the planning and design of a recycled water pipeline to help alleviate this deficiency.

On October 23, 2012, the Board of Supervisors took action to form a Community Facilities District (CFD) to generate revenue to construct this pipeline. To finance this project, the County will borrow money from the State Revolving Fund (SRF) loan program operated by the State Water Resources Control Board, and to repay that loan using the revenue stream generated by the CFD. It was intended that the CFD assessment would be placed on the Fiscal Year 2013-2014 property tax bills of the participants. However, due to project delays the deadline for placing the assessment on the tax rolls was missed, therefore the assessments must be direct billed or the revenue will be lost.

One of the requirements of the SRF loan is to enter into an agreement with NSD, who will own and operate the system once constructed.  Today's requested action is to approve that Agreement, which identifies the responsibilities of NSD (construction, operation and maintenance of the pipeline) and the County (payment of the majority of the cost). It is anticipated that the NSD Board will take their related action on June 4, 2014. The maximum cost anticipated under this Agreement is $9,859,000, the maximum loan amount.  The total construction cost of the Project is expected to range between approximately $11 Million and $13 Million, with 25% being covered by Federal grant funds obtained through the North Bay Water Reuse Authority.

Approval of Budget Transfer No. DPW012 increases appropriations by $145,000 in the Capital Improvement Program for the MST Recycled Water Pipeline (05001) with offsetting revenue from the SRF for Fiscal Year 2013-2014.  Payments will be made directly to NSD with offsetting proceeds from the State Loan.  Approval of Budget Transfer No. DPW013 establishes the CFD budget unit (Fund 2870).  For Fiscal Year 2013-2014, only administrative costs will be incurred which are estimated at $12,500 and will be offset by assessments collected from members of the CFD. 

In addition, Amendment 6 to the current agreement increases the contract by $131,000 for a new maximum amount of $2,798,250, to allow NSD to be reimbursed for engineering costs related to rebidding the two construction contracts due to a bid protest and NBWRA dues through FY 13/14.

PROCEDURAL REQUIREMENTS

1. Staff Report.
2. Public Comments.
3. Motion, Second, Discussion and Vote on the Item.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
The County is borrowing from the State Water Quality Control Board's Revolving Loan Fund (SRF) to pay for the cost of construction over the next two years. The loan - at an interest rate of 1.0% - must be repaid, over 20 years.  Revenue to support this comes from the special tax payments authorized by the Community Facilities District (CFD) mentioned above. The property owners who have annexed into the CFD will make payments totaling $601,465 per year for twenty years. That will enable the County to borrow $9,859,000 to cover 75% of the cost of the Project, with the other 25% coming from Federal grants already received.
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The groundwater deficiency in the MST area has been exacerbated by recent drought conditions and has resulted in significant decreases in property values in that area, a trend that is likely to continue without such an intervention.
Is the General Fund Affected
No
Future Fiscal Impact?
The proceeds from the CFD will accrue annually over the next 20 years. That money is designated solely for this purpose.
Consequences if not approved
As mentioned above, the pipeline project would not move forward, thereby exacerbating the groundwater deficiency in the MST area.

Impact

ENVIRONMENTAL DETERMINATION: The Napa County Board of Supervisors, acting as a responsible agency purusant to the California Environmental Quality Act (CEQA) and State CEQA Guidelines , Section 15096, has considered the environmental effects of the Project both in a comprehensive Environmental Impact Report (EIR) - in December 2009 - and in a subsequent Addendum (November 2013). The Federal (NEPA) aspect of this Project has also been addressed - through both documents - and has been certified by the North Bay Water Reuse Authority - of which both the County and NSD are members - and its lead agency, the Sonoma County Water Agency.

Background

The Milliken-Sarco-Tulocay (MST) basin east of the City of Napa has been designated as a groundwater-deficient area for over 15 years. The County, in partnership with Napa Sanitation District (NSD), has been participating in the planning and design of a recycled water pipeline to help alleviate this deficiency.

On October 23, 2012, the Board of Supervisors took action to form a Community Facilities District (CFD) to generate revenue to construct this pipeline. In order to finance this project, the County will borrow from the State Revolving Fund (SRF) loan program operated by the State Water Resources Control Board (WRCB) at an interest rate of 1% for twenty years, and repay that loan using the revenue stream generated by the CFD. It was intended that the CFD assessment would be placed on the Fiscal Year 2013-2014 property tax bills of the participants.  However, do to project delays the deadline for placing the assessment on the tax rolls was missed, therefore the assessments must be direct billed or the revenue will be lost.

One of the requirements of the SRF loan is to enter into an agreement with NSD, who will construct, own and operate the system.  Today's requested action is to approve that agreement, which identifies the responsibilities of NSD (construction, operation and maintenance of the pipeline) and the County (payment of the majority of the cost). It is anticipated that the NSD Board will take their related actions on June 4, 2014. The maximum cost anticipated under this Agreement is $9,859,000, the maximum WRCB loan amount.

NSD has solicited bids for the construction of this Project and its two primary components - the pipeline and the booster pump station and two different sized projects. These bids were opened on April 2nd and 3rd. Approval of the WRCB loan is still pending but is anticipated to occur shortly.  Approval of the proposed agreement between NCD and the County is contingent upon WRCB loan approval so that once loan approval is received, all contracts can be executed immediately and construction started. 
 
The total construction cost of the Project is expected to range between approximately $11 million and $13 million, with 25% covered by Federal grant funds and, potentially, Proposition 84 grant funds as well.  Costs to date for environmental work, design, financing and staff costs were funded from Measure A proceeds.  Some future costs, staff time and NBWRA dues, will also be funded through Measure A.  The total Measure A Funds utilized is estimated to be $4.8 Million.

Approval of Budget Transfer No. DPW012 increases appropriations by $145,000 in the Capital Improvement Program for the MST Recycled Water Pipeline (05001) with offsetting revenue from the SRF for Fiscal Year 2013-2014. Payments will be made directly to NSD with offsetting proceeds from the State Loan. Approval of Budget Transfer No. DPW013 establishes the CFD budget unit (Fund 2870). For Fiscal Year 2013-2014, only administrative costs will be incurred which are estimated at $12,500 and will be offset by assessments collected from members of the CFD.

In addition, Amendment 6 to Agreement 7350 increases an existing contract between NSD and the County by $131,000 for a new maximum amount of $2,798,250, to allow NSD to be reimbursed mainly for engineering costs.  The increase is related to rebidding the contracts to resolve a bid dispute and avoid costly litigation.  The amendment will also allow 50% reimbursement of NSD's NBWRA dues through the end of FY 2013/2014.  Going forward, NBWRA dues will be reimbursed through the new proposed agreement.