Steven Lederer - Director of Public Works - Public Works
Report By
German Sierra-Frutos - Junior Engineer - 8372
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
650 Imperial Way Building Window Replacement and Exterior Painting Project, PW 13-04 - Award of Construction Contract
Recommendation
Director of Public Works requests award of the contract for the "650 Imperial Way Building Window Replacement and Exterior Painting Project," PW 13-04, to Home Tech Remodeling Inc. of Folsom, California for the low base bid of $198,950 and authorization for the Chairman to sign the construction contract.
Summary
On February 25, 2014, the Board of Supervisors approved plans and specifications for the "650 Imperial Way Building Window Replacement and Exterior Painting Project," PW 13-04 and authorized the Director of Public Works to advertise for sealed bids. Bids were opened on April 24, 2014 with the apparent low bidder being Home Tech Remodeling Inc. of Folsom CA, in the amount of $198,950.
Home Tech Remodeling Inc. is not a local vendor.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The 650 Imperial Way building exterior walls and windows are in need of improvements to protect the building integrity and to make it more energy efficient.
Is the General Fund Affected
Yes
Future Fiscal Impact?
Construction cost will be incurred during Fiscal Years 2013-2014 and 2014-2015.
Consequences if not approved
Improvements to the building exterior walls, windows and handrails will not be made, and building integrity will continue to deteriorate.
Additional Information
The total project is estimated to cost $258,000 of which $203,000 is set aside for construction and $55,000 for contingencies, engineering and inspection costs. Appropriations available for this project in Fiscal Year 2013-2014 is $268,811. Unspent appropriations will be rolled over to Fiscal Year 2014-2015.
Impact
Categorical Exemption Class 1. It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See class 1 ("Existing Facilities") which may be found in the guidelines for the implementation of the California Environmental Quality Act at CCR Section15301, see also Napa County's Local Procedures for Implementing the California Environmental Quality Act Appendix B].
The project site is not on any of the lists of hazardous waste sites under Government code section 65962.5.
Background
The project includes window replacement, sealant replacement around window frames and exterior painting of the 650 Imperial Way building. The existing windows at the 650 Imperial Way building are aluminum fixed single and dual glaze. The windows in the building are not energy efficient and the existing sealant around the windows is failing. Hairline cracks in the paint are visible on the exterior walls of the building and the paint is deteriorating.
The proposed project will provide for:
1. Replacement of all single and double pane windows with new energy efficient dual pane windows and replacement of the seals around the new windows in the building. 2. Application of elastomeric paint on the exterior walls to enhance the waterproofing capability of the wall panels.
On February 25, 2014, the Board of Supervisors approved plans and specifications for the "650 Imperial Way Building Window Replacement and Exterior Painting Project", PW 13-04 and authorized the Director of Public Works to advertise for sealed bids pursuant to section 201150.8 of the Public Contract Code. Bids were opened on April 24, 2014 with the following results:
Contractor
City
Bid Amount
Home Tech Remodeling Inc
Folsom, CA
$198,950
Color Chart, Inc.
San Bruno, CA
$243,000
Industrial Coating and Restoration
Oceanside, CA
$250,623
Fix Painting Company
Woodland Hills, CA
$283,821
Onpoint Construction
Burlingame, CA
$292,370
Ionian Construction
Millbrae, CA
$313,000
T&M Painting and Construction
Lake Elsinore, CA
$314,279
Pinguelo Construction
Fairfield, CA
$327,764
The engineer's estimate was $203,000. Staff recommends award of a construction contract to Home Tech Remodeling Inc. of Folsom, CA in the amount of $198,950. Home Tech Remodeling Inc. is not a local vendor. To encourage local vendors, staff published a Notice to Contractors in the Napa Valley Register, reached out to the local builders exchange, and posted the invitation for Bid on the County's website. Public Contract Code requires that the construction contract be awarded to the lowest responsive bidder regardless of whether the low bidder is local or not. Once a construction contract is awarded, staff will notify the Workforce Investment Board (WIB) of the project and will require the Contractor to contact the WIB so that they can advise the WIB of any hiring needs.
During the bidding process, a comment was received objecting to the proposed plans and specifications. The comment letter opined that the elastomeric paint would not stick to the building, and that the exterior perimeter frame caulking needed to be replaced. Public Works staff investigated these two claims, and determined;
1) Staff reviewed the elastomeric paint chosen with the manufacturer, and determined that the same paint had been used successfully in identical applications. It is possible that the commenter was not aware that the specifications required a base coating (much like a primer used prior to painting a room in a house) that provides a base for the paint to adhere to. 2) Staff agrees that the external window seals, gaskets and all caulking at the perimeter of the existing window frames need to be replaced; this requirement was already included in the specifications and was clarified in Addendum Number 1 to the bid package.
The commenter's proposed solution would have increased the price of the project by several hundred thousand dollars and thus the suggestion for full replacement of windows (glass and aluminum frames) was not implemented.
Construction is scheduled for completion in the Summer of 2014.