Subject
Acceptance of a Community Development Block Grant (CDBG) totaling $1,500,000 for replacement of three water tanks in the Lake Berryessa Resort Improvement District
Recommendation
Director of Housing and Intergovernmental Affairs requests approval of the following actions relating to the Community Development Block Grant (CDBG) grant:
Acceptance of the grant in the amount of $1,500,000 for the replacement of three water tanks in the Lake Berryessa Resort Improvement District; and
Approval of and authorization for the Chair to sign a subgrant agreement with the Lake Berryessa Resort Improvement District in the amount of $1,447,675.
Summary
In April 2014, Napa County submitted an application for CDBG funding to assist the Lake Berryessa Resort Improvement District (LBRID) in replacing three existing redwood potable water storage tanks with three bolted steel water storage tanks to benefit approximately 180 housing units. The grant of $1,500,000 was awarded and staff received notification on January 9, 2015.
The action is to accept the grant and authorize the Director of Housing and Intergovernmental Affairs or the Assistant County Executive Officer to execute the Standard Agreement and a subagreement with the Lake Berryessa Resort Improvement District for the project.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
Community Development Block Grant Funds
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The County applied for a Community Development Block Grant for replacement of three water storage tanks on behalf of the Lake Berryessa Resort Improvement District. The water storage tanks are very old and past their useful lives. If this item is not approved, LBRID will not have funds to complete the water tank replacement project. Of the $1,500,000 in funds, $1,447,675 will go to the Lake Berryessa Resort Improvement District for the project and the County will retain $52,326 to cover administrative costs associated with managing and reporting on the grant.
Is the General Fund Affected
No
Future Fiscal Impact?
Funds will be budgeted and the project complete in Fiscal Year 2015-2016.
Consequences if not approved
The old tanks will remain and LBRID would continue to make costly repairs to maintain the aged system.
Impact
Consideration and possible adoption of a Categorical Exemption Class 1:It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]
Background
The Lake Berryessa Resort Improvement District (LBRID) is a dependent special district located within the unincorporated area of Napa County know as Pope Valley, California, established in 1965 to provide potable water and sewer services to a planned and recreation community (Berryessa Estates) along the northwestern shoreline of Lake Berryessa. The District was formed under the Resort Improvement District Law, Public Resources Code 13000. The LBRID service area covers an area of approximately 3 square miles and an adopted sphere of influence area of 225 acres.
The District provides water and wastewater services to a very small, rural community of 180 single-family residential properties and one commercial property. LBRID is the owner of the water system and the three water tanks proposed for replacement; however, the Napa County Board of Supervisors serves as the Governing Board for LBRID and appoints a District Engineer, which has historically been the County Director of the Public Works Department. The District Engineer serves as the chief administrative officer for LBRID. No other service agency provides water or waste water services in LBRID's boundaries.
LBRID's water supply is drawn from Putah Creek, a tributary to Lake Berryessa. The District's right to draw water from Lake Berryessa is secured through a 1999 agreement with the Napa County Flood Control and Water Conservation District. LBRID's water system consists of three pressure zones that are each maintained by their own storage tank. All three tanks have been in service since the mid 1960's and are at the end of their useful service life and two tanks have been determined to be unstable. Furthermore, the existing pumps, motors and starters at the two pump station are consistently in need of repair, which requires the District to rent emergency pumps to transfer water to the different pressure zones.
In general, incorporated cities under 50,000 in population and counties with an unincorporated area population of under 200,000 persons are eligible to participate in the State CDBG Program. To be eligible for funding, every CDBG-funded activity must meet one of the following three National Objectives of the program. The objectives include: benefit to low and moderate income persons, prevention or elimination of slums or blight and an urgent need, which is meeting other community development needs having a particular urgency because of existing conditions that pose a serious and immediate threat to the health or welfare of the community. The County can apply for funding on behalf of other local entities where the County acts as a pass through for funds to ensure all activities funded by CDBG meet the qualifications of the grant.
In April of 2014, after meeting all the public noticing requirements, the County submitted an application for CDBG funding totaling $1,500,000 for the project. The application was successful and the Standard Agreement for release of the funds from the state arrived in January 2015. Staff recommends acceptance of the grant and Standard Agreement and the execution of a subagreement with LBRID, so the funds can be used for the water storage tank project.