Amendment #1 to Agreement 6199 for the Devlin Road Extension Project
Recommendation
Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 1 to Agreement No. 6199 with Stahr & Associates, Inc. increasing the amount by $5,400 for a new maximum of $15,000 and extending the term through June 30, 2005 for appraisal of land needed for the Devlin Road extension project.
Summary
Approval of the requested amendment will provide for additional compensation for unanticipated work relating to appraisals used to determine and offer just compensation to the property owners affected by the Devlin Road extension Project. The appraisals were utilized to make the offers of just compensation to the affected property owners on March 25, 2004. The making of the offer of just compensation by the County to the property owners was one of the required findings made by the Board in considering adoption of the Resolution of Necessity at the May 4, 2004 Hearing.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Obtaining appraisals is necessary for the property acquisition process. Property acquisition is necessary to build the road.
Is the General Fund Affected
No
Future Fiscal Impact?
No additional property acquisition is necessary at this time and it is anticipated that no additional appraisals nor funds will be necessary.
Consequences if not approved
Appraiser will not be compensated for additional work performed necessary to complete the original appraisals.
Additional Information
None
Impact
CEQA STATUS: Mitigated Negative Declaration Prepared: According to the Mitigated Negative Declaration, which was adopted by the Board on October 22, 2002, the proposed project would have, if mitigation measures are not included, potentially significant environmental impacts in the following areas: Biological Resources, Noise, Air Quality and Transportation/Traffic. This project site is not on any of the list of hazardous waste sites enumerated under Government code section 65962.5
Background
The County Public Works/Road Department is developing plans for the extension of Devlin Road from its northern terminus in the Napa Valley Gateway Development north to its eastern terminus from Soscol Ferry Road. This extension will require the acquisition of right of ways on four parcels of land: APNs 057-020-006, 057-020-018, 057-210-002 and 057-020-025.
On December 2, 2003, the Board approved Agreement No. 6199 with Stahr & Associates, Inc. for a maximum of $9,600 for the term December 2, 2003 through June 30, 2004 for appraisal of parcels of land needed for the Devlin Road extension project.
The work under the original agreement has been completed. Amendment No. 1 to the original agreement for $5,400 is necessary for unanticipated work related to the original appraisals to show the acquisition of temporary construction easements and temporary drainage easements also needed for the construction of the project. The appraisals were utilized to make the offers of just compensation to the affected property owners on March 25, 2004. The making of the offer of just compensation by the County to the property owners, required by Government Code Section 7267.2, was one of the findings made by the Board in considering adoption of the Resolution of Necessity at the May 4, 2004 Hearing. At the Hearing the Board adopted a resolution determining that the public interest and necessity require the filing of eminent domain proceedings. Eminent domain proceedings are in progress. The amendment also provides for contingency and contract time extension for possible additional work related to litigation during the eminent domain proceedings.