On January 27, 2015, the Board approved Amendment No 23 to Agreement No. 4202, with Napa County Flood Protection and Watershed Improvement Authority, increasing Measure "A" appropriations on four approved projects for additional scope of work and extending the agreement through June 30, 2016. When the Authority met later that day, the Authority Board requested the Amendment be modified to remove additional funding for the Angwin water supply reliability projects pertaining to funding a replacement well for Pacific Union College until questions could be resolved about the use of the water from the well. The Authority approved the modified Amendment No. 23.
Measure "A" Background
In March 1998, voters approved a half cent sales tax increase for flood control purposes known as Measure "A". The County and each City and Town are entitled to the proceeds from Measure "A" generated within their political boundaries for projects that were specified in the ballot measure. For the County, the Measure reads:
Unincorporated Areas of Napa County:
- County unincorporated area flood damage reduction projects including elevating/relocating structures, including bridges, in the floodway and floodplain; and
- Agricultural watershed and stormwater runoff management improvements planned jointly by the agricultural industry, the County, the Napa County Resource Conservation District and the Department of Fish and Game, including projects which will:
- Reduce the amount of storm runoff and sediment in the Napa River System from agricultural lands; and
- Increase flood storage of the River system by the setback of active land uses from river and tributary banks.
Community of Angwin/Deer Park:
- Stabilization and enhancement of existing water reservoirs which shall be for the purpose of flood protection and water reliability; and
- Stabilize water quality.
Additional Funding Allocations for Existing Projects
Staff is requesting approval for additional Measure "A" funding for the following new activities for the following existing projects through the end of Fiscal Year 2015-2016, and revised Amendment No. 23 as was approved by the Flood Authority Board on January 27, 2015:
Milliken Sarco Tulocay Recycled Water Project
An additional $200,000 of funding to support staff labor, legal and consultant costs, and North Bay Water Reuse Authority (NBWRA) dues through the end of FY 2015-2016.
Napa River Oakville to Oak Knoll Reach Restoration Project
The environmental review of the project has been completed and permit applications have been submitted, The first two phases of construction (Restoration Groups A and C) are planned in summer 2015 and 2016 supported by three awarded grants from the EPA, totaling approximately $2.3M. The two most recently awarded grants require match funds of $948,000, which are included in the Amendment No 23. Staff further recommends an additional $582,000 of funding to support completion of project design through Group C, $100,000 for staff labor and $70,000 to support landowner liaison costs through the end of FY 2015-2016, for a total of $1,700,000 of new Measure "A" funding for this project.
Milliken Creek Flood Reduction Project
This project was approved in Amendment 19 to address flooding concerns along Milliken Creek in the Kaanapali Drive area. A $500,000 grant has been awarded to support construction of flood reduction improvements and to eliminate a fish passage barrier on the creek. The design of the Project is underway and Silverado Resort, as part of its contribution as a project partner, has submitted permit applications to the Department of Fish and Wildlife to construct a replacement bridge and water diversion, which replaces a dam that must be removed to accomplish the flood reduction and fish passage improvements. Staff recommends additional funding of $200,000 to support completing the design and staff labor costs for this project through FY 2015-2016.
Measure "A" Funding Agreement
In August 1999, a Funding Agreement was entered into between the County and the Napa County Flood Protection and Watershed Improvement Authority (NCFPWIA), and is the mechanism for the County to receive Measure A funding to conduct projects as specified in the Measure "A" Ordinance. The Funding Agreement is amended to provide funding on an annual basis, or if necessary, as additional projects or tasks on previously approved projects are identified. The County Funding Agreement was last amended on April 1, 2014; as of this 22nd amendment, the NCFPWIA had authorized a total of $31,662,000 towards fourteen approved Measure "A" projects in the County unincorporated area. The total Measure "A" expenditures through the end of the previous fiscal year (6/30/14) is $24,281,587 as summarized in the attached spreadsheet.
In total, staff is requesting approval of an additional $2,100,000 for the additional activities on the above three projects in Amendment No. 23. $782,000 is required for remainder of Fiscal Year 2014-2015 and the remaining $1,318,000 will be included in the Fiscal Year 2015-2016 budget. Approval of Budget Transfer No. DPW-006 appropriates an additional $582,000 in the Napa River Restoration Oakville to Oak Knoll Reach Program budget and an additional $200,000 in the Milliken Creek Flood Reduction Program budget. Upon approval of Amendment No. 23, the total authorized funding for the fourteen approved projects will be $33,762,000.
Measure "A" Revenues and Forecast Expenditures
The attached spreadsheet provides updated audited revenues and expenses through the end of FY 2013-2014, and budgeted revenues and expenses for the current fiscal year ending June 30, 2015. It also includes forecast expenditures on approved projects, which are subject to future Board approval. The requested funds included in Amendment No. 23 are included in the budget allocation and expense forecasts. The revenue and expense forecast has been extended through June 30, 2019 (FY 2019), which is one year beyond the end of the 20-year Measure "A" tax. This forecast illustrates the projected funding that is expected to be available for potential future additional projects and activities on existing projects, subject to future Board approval. In accordance with the JPA, the expected revenues have been allocated between the three areas within the unincorporated area: 17% for projects within the Angwin area, 7% for projects in the Lake Berryessa/Putah Creek Watershed and the remaining 76% for the balance of the unincorporated area. For forecast illustration purposes, the spreadsheet shows future available annual revenues for Angwin and Lake Berryessa area projects roughly equally for the remaining years of the tax measure. For the remaining areas of the County, the forecast illustrates the expected costs for activities on existing ongoing projects, which are expected to utilize all remaining available funds to complete these projects. Notably, in FY 2016 and beyond, three projects are expected to
utilize remaining Measure A revenues outside the Angwin and Lake Berryessa areas: The Napa River Oakville to Oak Knoll Restoration Project (projected completion in FY 2019), the MST Recycled Water Project (complete in FY 2016) and the Milliken Creek Flood Reduction Project (complete in FY 2017).