The Hall of Justice (HOJ) and Jail Annex suffered damage during the recent South Napa Earthquake. Portions of all three floors of the HOJ remain uninhabitable for various reasons, including significant water damage to suspended ceilings, carpeting and partition walls, damage to mechanical equipment housed in the penthouse, and damage to the building exterior envelope. The building is currently yellow tagged, which allows only restricted occupancy. It was therefore necessary to relocate portions of various County Departments (Corrections, Probation, District Attorney, Parks, and the Fire Marshall) in order to assess the damage, prepare repair designs and construct the repairs.
Nacht & Lewis Architecture, Inc. was selected through a qualifications based selection process to provide architectural/engineering and associated services for the implementation of Hall of Justice and Jail Annex earthquake repair projects. A contract was entered into in October, 2014 to perform initial assessment and architectural services.
A brief summary of the critical path work to reestablish occupancy is provided below:
Building Envelope:
In order to return the building envelope to pre earthquake strength, an epoxy injection process is being piloted in small areas of the building to determine the most effective method of injecting the epoxy into the structure cracks. Following the epoxy pilot test, the complete epoxy repair project will be designed and bid.
In a parallel effort, we have engaged an independent structural engineer to review calculations and determine if re-occupancy can occur before all the epoxy work is complete.
Third Floor (Corrections):
Several mostly non-structural cracks, caused by the earthquake, and various other earthquake related damage, must be repaired in order to reoccupy the limited number of inmate cells that are currently damaged. This is known as the “grout” project, as the majority of the work involves grout installation in various cracks. The County is preparing to send the grout project out to bid. The Epoxy and the Grout projects are both critical path to re-occupying the third floor.
Second Floor (Probation)
Repairs to the second floor resulted from significant water damage, including ceilings, walls, and floors. Code upgrades, both planned before the earthquake and those triggered by the repairs, include improved exiting, seismic bracing, and corridor rating improvements. These upgrades will be done concurrently with the earthquake repair project. This will likely be the last area reoccupied due to the extent of needed repairs.
First Floor (Parks, Fire Marshall, Corrections, Probation)
Needed repairs to the first floor include ceilings, walls, and floors. The concrete structural ceiling in certain areas of the first floor also requires repair. Minor code upgrades, though much less extensive than on the second floor, may also be required but will not need to be completed until after re-occupancy of this area.
Current Status and Contract Amendment
To date the County has completed the design and will commence bidding and starting physical work (pending FEMA approval) to repair dislodged grout and cracked floor tiles in the third floor of the Hall of Justice. The County has also awarded a contract to complete the pilot epoxy injection project to help assess the most cost effective way to repair damage associated with the building envelope. Start of this work is subject to FEMA approval. Based on the results of the pilot work a more comprehensive design will be developed to epoxy inject the remainder of the structure.
This contract amendment is for the design services needed for the remaining epoxy work. It is also for repair to the second floor, the first floor structural ceiling, and critical systems in the penthouse of the Hall of Justice.
Future amendments to cover all remaining damage including but not limited to damage to the First Floor, Jail Annex and the seismic joint between the Jail Annex and Hall of Justice will be presented to the Board of Supervisors over the coming months.