Submitter

Director
Steven Lederer - Director of Public Works - Public Works
Report By
Annamaria Martinez - Assistant Engineer - 259-8378
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
Amendment No.1 to Professional Services Agreement with Agreement with Mead & Hunt - Milliken Creek Flood Reduction Project

Recommendation

Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 1 to Agreement No. 8200 with Mead & Hunt, increasing the contract amount by $139,593 for a new maximum of $363,888, and amending the scope to include the design of the fish passage barrier removal within Milliken Creek and the associated restoration and revegetation activities that were not included in the original scope of the Milliken Creek Flood Reduction Project.

Summary

Mead & Hunt was selected through a Request for Proposals (RFP) process to complete the design for the Milliken Creek Flood Reduction and Fish Passage Barrier Removal Project in March 2014.  Amendment No. 1 to Agreement No. 8200 will add the design services for removal of the fish passage barrier within Milliken Creek and the associated restoration and revegetation activities that were not included in the original scope of the Milliken Creek Flood Reduction Project. 

Mead & Hunt is not a local vendor.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Additional Services are needed to complete plans and specifications for the project under Agreement No. 8200.
Is the General Fund Affected
No
Future Fiscal Impact?
The project is expected to continue to FY 2016-2017.  Appropriate funds are included in the FY 2015-2016 budget.
Consequences if not approved
The fish passage barrier would not be removed from Milliken Creek.  Potential loss of revenue from granting agencies and homeowners for flood reducing activities along Milliken Creek near Kaanapali Drive.

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.  The project will be evaluated under the CEQA process as a part of its development.

Background

In December 2005, the Kaanapali Drive neighborhood, northeast of the intersection of Atlas Peak Road and Hillcrest Drive experienced unprecedented flooding which resulted in damage to several homes. In response to the flooding, the County entered into an agreement with the Silverado Property Owner’s Association (SPOA) to cost share a flood reduction and stream bank stabilization study of Milliken Creek from Atlas Peak Road to Westgate Drive. The firm chosen by the SPOA was Hydrologic Systems Inc (HSI). The study was completed in December 2007. It focused on the hydrology, geomorphology, and hydraulics of the Milliken watershed and identified preliminary alternatives to reduce flooding in the study area; it also identified portions of Kaanapali Drive as areas subject to flooding from a 100-year flood event. A hydraulic model was developed by HSI to study flooding at various flood frequencies. Potential flood reduction alternatives identified included increasing culvert capacities, redirecting certain drainage courses, construction of berms to detain overbank flows in existing or created impoundment areas, modifications to the upstream Milliken Dam to attenuate flood flows, and several combinations of these alternatives that would maximize the reduction of possible flooding.

As a result of the study, County staff worked with FEMA to map a Special Flood Hazard Area (SFHA) on Kaanapali Drive. The original study did not contain enough information to establish base flood elevations (BFEs) for the SFHA, so in August 2010, the County continued the hydrology and hydraulic analysis of the Milliken Creek watershed to its termination into the Napa River. The purpose of the new study was not only to establish BFEs, but also to evaluate possible additional improvements for additional flood reduction possibilities.

In March 2010, the County hired Riechers Spence and Associates (RSA) to perform a cost benefit analysis for the project alternatives identified in the original report. RSA was able to incorporate existing known data into their analysis, and also evaluated several additional flood reduction alternatives. In December 2011, RSA completed their cost-benefit analyses; based on their evaluations, the following alternatives were recommended for this Project: 

1. Removal of an existing dam which is a barrier to fish passage and restoration of the Milliken Creek channel. 
2. Restoration of the overland release path through Hillcrest Drive and Atlas Peak Road.
3. Strategic flood proofing on the south, north, and east side of Kaanapali Drive.

Based on the recommendations in the RSA report and a request for support from several Kaanapali Drive homeowners, the Board approved the use of Measure A funds in 2012 to implement a flood reduction project.  During 2013, staff worked with property owners and Silverado Resort to reach concurrence on project objectives and awaited the property owner's formation of a Homeowners Association (HOA), which could enter into an agreement with the County and the Resort.  The Kaanapali Drive HOA was approved by the property owners in January 2014.   A Request for Proposals for design of the above flood reduction improvements was issued on January 31, 2014. Interviews were held on March 19 and 20, and based on previous experience with similar projects, Mead & Hunt out of Sacramento was chosen as the most qualified firm.

The County, Silverado Resort and the HOA have been working toward entering into a project agreement for implementation of the project.  The draft project agreement calls for Silverado resort to construct a replacement bridge in advance of the removal of the existing dam.  In the interest of advancing the design so that awarded grant funds were not jeopardized, Agreement No. 8200 for professional services related to design costs for all project elements with the exception of dam removal and stream restoration was signed in August 2014.  The intent was to return to the Board with this amendment once the Silverado Resort moved forward with their bridge project.  At this time, Silverado has advanced their design, applied for, and received a draft permit to construct the replacement bridge. 

Because the Resort has verbally committed to replacing the dam, staff is now requesting Board approval of Amendment No. 1, increasing the compensation and scope of Agreement No. 8200 so that Mead & Hunt can continue their design efforts.  The goal is to be in a position to advertise a construction contract for the flood reduction project in spring 2016.  The project agreement between the Resort, the HOA and the County will be brought forward for Board approval as a separate item in the coming weeks once the agreement is finalized.

Attachments

There are no attachments to this item