- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- Yes
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- Design of the project has been completed and approval of the plans and specifications and authorization to advertise for bids is required in order to move the project into the construction phase.
- Is the General Fund Affected
- No
- Future Fiscal Impact?
- Design and construction costs are expected to be incurred during Fiscal Year 2015/2016.
- Consequences if not approved
- The project will not go out for construction bids.
- Additional Information
- The Board has approved a project budget of $638,000 for Fiscal Year 2015-2016. The engineer's estimate for construction is $875,000, and the overall estimated cost of the project is $1.0 million.
On August 11, 2015, the Board approved an amendment to the agreement with the City of Calistoga to fund the shortfall in the budget. Based on that action, there will be a future budget transfer to make up the required difference.
Cost increases are due to a lengthy approval process with the City of Calistoga for the project as well as the negotiation of the City's financial participation, resulting in cost escalation since the project began in 2011. Additionally, due to the site's historic significance, costs also include the effort to restore and preserve some materials, rather than replace them. Also, finalizing the project design revealed some additional needs, such as facilities rental during construction, and a self-check machine, also contributing to costs. Finally a portion of the increases are due to compliance with new code regulations for lighting performance and control systems.