Studies have been completed for Hopper Creek, and a combination of upstream detention, downstream sediment management and creek capacity measures have been selected as methods of reducing flooding in the Town of Yountville. The additional funds will be used to construct the Hopper Creek improvements - Project No. 6. The proposed Amendment No. 10 will reallocate the balance of $28,456 from the debt service for the Flood Barrier Project to Project No. 6, as well as add $3,177,544 to Project No. 6, bringing the total amount for Project No. 6 to $3,206,000.
PROCEDURAL REQUIREMENTS
- Staff reports.
- Public comments.
- Motion, second, discussion and vote on the item.
In March 1998, voters approved a half-cent sales tax increase for flood control purposes known as "Measure A". The County and each City and Town are entitled to the proceeds from Measure A generated within their political boundaries for projects that were specified in the ballot measure. For the Town of Yountville, the measure reads:
Town of Yountville
- Flood protection for the Town's mobile home parks and surrounding areas; and
- Hopper Creek and Beard Ditch improvements and restoration for flood protection.
The projects being implemented by the Town of Yountville comply with the Measure. These projects are: 1) Flood Barrier Project for two mobile home parks; 2) Phase I Hydrologic Study of the Hopper and Hinman Creek Watershed; 3) Phase II Hydrologic Study & Design of the Hopper and Hinman Creek Watershed; 4) Hopper Creek Diversion Structure Bank Stabilization; and 5) Beard Ditch Bank Repair. The debt service for the Flood Barrier Project and the Phase II Project are ongoing projects and the rest of the other projects are complete.
The Town now wishes to add $3,177,544 to its Agreement to fund the construction of the Hopper Creek Improvements Project (HOP): HOP 5, HOP 10, Villagio Channel, and Sedimentation Basins (Project No. 6), and to reallocate $28,456 from the debt service for the Flood Barrier Project to Project No. 6, bringing the total approved funds for Project No. 6 to $3,206,000. Project No. 6 stems from the studies conducted under Project Nos. 2 and 3 (Hydrologic Study & Design of Hopper Creek). The Town is proposing to construct four separate flood and sediment control projects to reduce flooding from Hopper Creek, and to control the transport of sediment in Hopper Creek and Villagio Channel ( a tributary to Hopper Creek). Project No. 6 is comprised of the following:
- Install a flood flow diversion structure in Hopper Creek with pipeline along Finnell Road to divert flow to Beard Ditch. The work includes flow diversion structure in Hopper Creek, storm drains along Finnell Road, the outfall at Beard Ditch and the necessary minor storm drainage, sewer, water and roadway improvements.
- Stabilize approximately 300 linear feet of Hopper Creek between Highway 29 and Washington Street.
- Stabilize approximately 450 linear feet of the bank of the Villagio Channel.
- Construct two sediment basins in Hopper Creek, and one sediment basin at Mulberry Street and one at Oak Circle.
Because the Town had incurred some expenses prior to the amendment of this Agreement, Amendment No. 10 will have an effective date of June 1, 2015.
Since the execution of Agreement No. 18 between the NCFPWIA and the Town of Yountville, there have been nine amendments to the Agreement. As of Amendment No. 9, the maximum total amount approved was $5,429,981.71. These amendments are as follows:
The original Agreement between NCFPWIA and the Town of Yountville was executed in 2003 in the amount of $400,000 to fund a portion of the Town's Flood Barrier Project providing flood protection to the two mobile home parks (Rancho de Napa and Gateway Mobile Home Parks), which experienced flooding from the Napa River. The two primary features of this project consist of a continuous floodwall and an interior detention basin and storm drain pump station, which terminates at Beard Ditch. The Town issued bonds to pay for the majority of project costs up front. Amendment No. 1 of the Agreement set up annual payments (through the year 2018), reimbursing the Town for debt service payments on those bonds based on a preliminary debt service schedule. Amendment No. 2 of the Agreement added additional funding for debt service interest.
Amendment No. 3 provided an additional $156,000 for Fiscal Year 2007/2008 where the funds were allocated as follows: 1) $56,000 to conduct a hydrologic study of the Hopper and Hinman Creek Watershed; 2) $50,000 to study the feasibility of increasing the bridge capacities of Mulberry Street and Oak Circle and the restoration of this portion of the creek; and 3) $50,000 to design and construct a bio-engineered structure on Hopper Creek that will divert large storm flows to Beard Ditch. This structure includes rip rap bank protection immediately downstream of the structure, which protects two large oak trees from being undermined. The project involved the design of a bio-engineered solution to restore the stream bank and save the trees at this location.
Amendment No. 4 allowed previously approved funds in Fiscal Year 2007/2008 to roll forward into Fiscal Year 2008/2009, as long as the total compensation for projects under this Agreement did not exceed amounts previously approved.
Amendment No. 5 added $185,000 for Fiscal Year 2009/2010 where the funds were allocated as follows: 1) $85,000 for the Hopper Creek Diversion Structure Bank Stabilization, which comprised the removal of vegetation and stream sediment deposits, removal of an existing stone retaining wall and installation of a new retaining wall, and reshaping the top of bank to allow for planting of native vegetation; and 2) $100,000 for the Phase II hydrologic study to complete the design,engineering and prioritization of the projects identified in Phase I.
Amendment No. 6 added an additional $80,000 to the contract where the funds were allocated as follows: 1) $55,000 added to the ongoing Phase II Hydrologic Study of the Hopper and Hinman Creek Watershed Project ($100,000 for this project was previously approved in Amendment Nos. 2 and 5). The remaining $25,000 was allocated to the Beard Ditch Bank Repair. In 2004, the Town of Yountville constructed a floodwall barrier around the Gateway and Rancho de Napa Mobile Home Parks. The rain water pumped from inside the floodwall to Beard Ditch caused erosion across the ditch. Funds were used to complete the design, obtain permits and complete repairs to Beard Ditch.
Amendment No. 7 provided an additional $125,000 for the ongoing Beard Ditch Bank Repair ($25,000 was previously approved in Amendment No. 6). This bank stabilization project consisted of excavating a foundation, installing rip rap and reshaping the bank and was completed in the summer of 2011. Amendment No. 7 also updated the debt service schedule previously approved in Amendment No. 1 with actual payments from Fiscal Year 2004/2005 through Fiscal Year 2010/2011, as well as revised the debt service payment from $289,071 to $265,970 for Fiscal Year 2011/2012.
Amendment No. 8 reallocated balances of $247,533 from projects that have been completed to the Phase II Hydrologic Study & Design of the Hopper and Hinman Creek Watershed Project (Phase II Study), as well as rolled forward $81,819 for the Phase II Study from Fiscal Year 2011/2012 into Fiscal Year 2012/2013. The Phase II Study was completed in October 2011. Based on the study, there are five to six projects with a combination of upstream detention, downstream sediment management, and creek capacity increasing measures that are possible methods of reducing flooding in the Town of Yountville. The funds are being used for design, CEQA document preparation and obtaining the permits before constructing the flood mitigation and creek restoration projects. Amendment No. 8 also updated the debt service payments to reflect the actuals from Fiscal Year 2004/2005 through Fiscal Year 2011/2012 and the future payment schedule to reflect lower interest payments as a result of a refinancing of the debt leaving a balance of $129,832.90 in the agreement to be reallocated in a future agreement to another approved project. Additionally, the Amendment allowed remaining unspent funds in the previous fiscal year to automatically roll over to the next fiscal year for the respective approved activities. Amendment No. 8 did not change the previously approved amount of $4,559,814 for the Town of Yountville.
Amendment No. 9 reallocated the balance of $129,832.90 from the debt service for the Flood Barrier Project to the Phase II Project and added $870,167.71 to the Phase II Project, bringing the total approved funds for the Phase II Project to $1,402,533. The additional funds were to support the design, environmental clearance, permits and construction for flood control improvements on Hopper Creek. Hopper Creek flood control improvements are part of the Phase II Study.
The contract funding history is provided in the table below:
CONTRACT FUNDING HISTORY
| |
Date |
Purpose |
Amount |
Contract Maximum |
| Original Contract |
08/12/03 |
Original Contract |
$400,000 |
$400,000 |
| #1 |
04/06/04 |
Debt service Fiscal Year 2004/2005 - Fiscal Year 2017/2018 |
$3,680,098 |
$4,080,098 |
| #2 |
06/21/05 |
Debt service interest payment |
$40,797 |
$4,120,895 |
| #3 |
11/06/07 |
Feasibility Study/Hydrologic Study Part I and Hopper Creek Structure |
$156,000 |
$4,276,895 |
| #4 |
06/24/08 |
Extends Amendment #3 funding to Fiscal Year 2008/2009 |
$0 |
$4,276,895 |
| #5 |
10/20/09 |
Hopper Creek/Hydrologic Study Part II |
$185,000 |
$4,461,895 |
| #6 |
06/29/10 |
Hydrologic Study Part II/Beard Ditch Bank Repair |
$80,000 |
$4,541,895 |
| #7 |
08/09/11 |
Beard Ditch Bank Repair and update Debt Service Schedule |
$17,919 |
$4,559,814 |
| #8 |
10/02/12 |
Rolled balance of $81,819 from Fiscal Year 2011-2012 to Fiscal Year 2012/2013 for the Phase II Study, and reallocated $247,533 from balances of completed projects to the Phase II Study. Revised the debt service payment from $4,013,814.28 to $3,883,981.38. Allowed remaining unspent funds in the previous fiscal year to automatically rollover to the next fiscal year for the respective approved activities. |
$0 |
$4,559,814 |
| #9 |
6/4/13 |
Reallocate the balance of $129,832.90 from the debt service for the Flood Barrier Project to the Phase II Project, and add $870,167.71 to the Phase II Project |
$870,168 |
$5,429,983 |
| #10 |
8/11/15 |
Reallocate the balance of $28,456.08 from the debt service for the Flood Barrier Project to Project #6, and add $3,177,542 to Project #6 |
$3,177,542 |
$8,607,525 |
With the approval of Amendment No. 10, the funding summary of the six projects will be as follows:
| Projects |
Total Amount |
| #1 - Flood Barrier Project (Debt service) |
$3,883,981 |
| #2 - Phase I Hydrologic and Hydraulic Study of Hopper and Hinman Creek Watershed |
$49,604 |
| #3 - Phase II Hydrologic Study and Design of Hopper and Hinman Creek Watershed |
$1,402,533 |
| #4 - Hopper Creek Bank Stabilization |
$37,463 |
| #5 - Beard Ditch Bank Repair |
$56,400 |
| #6 - Hopper Creek Improvements Project: HOP5, HOP10, Villagio Channel, and Sedimentation Basins |
$3,206,000 |
| Grand Total |
$8,607,525 |