Award of Professional Service Agreement for Dry Creek Bridge Replacement Br No. 21C0056, RDS 15-22
Special Instruction
Recommendation
Director of Public Works requests approval of and authorization for the Chairman to sign an agreement with Biggs Cardosa Associates of Oakland, California for a maximum of $775,187 for the term November 8, 2016 through June 30, 2017 with an automatic extension provision for an additional year at the end of each fiscal year, not to exceed five additional years, for the design of Dry Creek Road Bridge (21C0056) Replacement Project, BRLO 5921(061), RDS 15-22.
Summary
On August 20, 2012, Caltrans issued a letter to Cities and Counties requesting local agencies to review their public highway bridges for potential replacement, rehabilitation, or preventive maintenance and to take necessary actions to address any public safety issues and to extend the life of our bridge inventory. County staff evaluated fourteen (14) bridges and seven (7) bridges were prioritized for the first phase of the Highway Bridge Program.
Bridge No. 21C0056 Dry Creek Road over Dry Creek is 92 years old and has the lowest Sufficiency Rating (SR) rating (18.0) of all the structures evaluated. The superstructure is showing signs of deterioration. The substructure, composed of stone masonry abutments, is in a state of decline and the bridge is considered critical. Additionally, the width of the roadway and the approach alignment are substandard.
Dry Creek Road Bridge is designated as an Off-System bridge and it is eligible for 100% Federal funding with Toll Credits as match for local funds. The total estimated project cost including design, environmental clearance, right-of-way, construction engineering and construction is approximately $6,700,000. Preliminary engineering funds (E76 for PE) have been approved for the amount of $899,260. The County share for disallowed staff billing rate and other expenses is approximately $71,678 for the preliminary engineering phase which will be supplemented by Roads funds.
In order to support this project and various other projects, the Napa County Public Works Department released a Request for Qualifications (RFQ) inviting consulting firms to provide On Call Engineering Support and Construction Support Services. Seven consultants submitted qualifications in response to this request for qualifications (RFQ) for Category 1 - Office Engineering. From this pool of seven consultants, the two shortlisted firms are Biggs Cardosa Associates, Inc. of Oakland, California and Moffat & Nichol, of Walnut Creek, California.
Public Works staff has identified the team led by Biggs Cardosa Associates as the most qualified team to provide the design services for the Dry Creek Road Bridge (21C0056) Replacement Project, BRLO 5921(061), RDS 15-22. Biggs Cardosa Associates is not a local vendor.
It is anticipated that preliminary engineering costs will occur in Fiscal Year 2016-17, FY 2017-18 and Fiscal Year 2018-19. Construction is anticipated to occur in Fiscal Year 2019-20. After completion of the preliminary engineering phase, CEQA/NEPA clearance and final design, staff will submit a request for authorization for the construction phase funds to the State of California Department of Transportation (Caltrans). All other future impact is limited to routine road maintenance as is currently performed.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The Dry Creek Road Bridge must be replaced. Failure to do so will ultimately result in the loss of use of the subject road.
Is the General Fund Affected
No
Future Fiscal Impact?
Dry Creek Road Bridge is designated as an Off-System bridge and it is eligible for 100% Federal funding with Toll Credit as match for local funds. The total estimated project cost including design, environmental clearance, right-of-way, construction engineering and construction is approximately $6,700,000. Preliminary engineering funds (E76 for PE) have been approved for the amount of $899,260. The County share for disallowed staff billing rate and other expenses is approximately $71,678 for the preliminary engineering phase which will be supplemented by Roads funds.
It is anticipated that preliminary engineering costs will occur in Fiscal Year 2016-17, Fiscal Year 2017-18 and Fiscal Year 2018-19. Construction is anticipated to occur in Fiscal Year 2019-20. After completion of the preliminary engineering phase, CEQA/NEPA clearance and final design, staff will submit a request for authorization for the construction phase funds. All other future impact is limited to routine road maintenance as is currently performed.
Consequences if not approved
The County will forfeit Federal Highway Administration grant funds, preventing this bridge from being replaced.
Impact
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.
Background
On August 20, 2012, Caltrans issued a letter to Cities and Counties requesting local agencies to review their public highway bridges for potential replacement, rehabilitation, or preventive maintenance and to take necessary actions to address any public safety issues and to extend the life of our bridge inventory. The County evaluated fourteen (14) bridges and the following seven (7) bridges were prioritized for the first phase of the Highway Bridge Program:
ITEM
BRIDGE NUMBER
LOCATION
SUFFICIENCY RATING
1
21C0056
Dry Creek Road over Dry Creek
18, SD
2
21C0075
Chiles-Pope Valley Rd over Chiles Creek
54.9, SD
3
21C0088
Soda Canyon Road over Soda Creek
47.5, FO
4
21C0080
Loma Vista Drive over Soda Creek
57.2, FO
5
21C0058
Hardin Road over Maxwell Creek
34.8, SD
6
21C0077
Conn Valley Rd over Conn Creek
42.5, FO
7
21C0074
Berryessa-Knoxville over Eticuera Creek
25.4, SD
The prioritizations of the bridges were based on the following:
Off system bridges because currently there is 100% funding available utilizing the Toll credits (which may be depletedin the future)
Location of the bridge, number of residents served and evaluation of the Average Daily Traffic (ADT)
Sufficiency ratings and flagged Structurally Deficient (SD) or Functionally Obsolete (FO)
Site visits and visual inspection
Feasibility of programming
On January 25, 2013, Public Works submitted Highway Bridge Rehabilitation & Replacement Program (HBRRP) applications to program the seven (7) bridges in the Federal Transportation Improvement Program (FTIP). The bridges are programmed to be completed over the next ten to fifteen years.
Bridge No. 21C0056 Dry Creek Road over Dry Creek is 92 years old and has the lowest SR rating (18.0) of all the structures evaluated. The superstructure is showing signs of deterioration, the substructure, composed of stone masonry abutments, is in a state of decline and the bridge is considered scour critical. Additionally, the width of the roadway and the approach alignment are substandard.
Dry Creek Road Bridge is designated as an Off-System bridge and it is eligible for 100% Federal funding with Toll Credit as match for local funds. The total estimated project cost including design, environmental clearance, right-of-way, construction engineering and construction is approximately $6,700,000. Preliminary engineering funds (E76 for PE) have been approved for the amount of $899,260. The County share for disallowed staff billing rate and other expenses is approximately $71,678 for the preliminary engineering phase which will be supplemented by Roads funds.
In order to support this project and various other projects, the Napa County Public Works Department released a Request for Qualifications (RFQ) inviting consulting firms to provide On Call Engineering Support and Construction Support Services. Seven consultant submitted qualifications in response to this request for qualifications (RFQ) for Category 1 - Office Engineering. From this pool of seven consultants, two firms were shortlisted based on the following five criteria:
Responsiveness to Request for Statement of Qualifications — breadth and depth of response; overall quality, responsiveness and completeness.
Organization and Technical Qualifications of the team (licenses and certifications held by the firm and key staff).
Relevant Experience and Expertise for the services. Proven experience and qualifications related to required services for the design and construction of public works capital improvement projects (roads/bridges/drainage systems).
Understanding and Approach. Availability and ability of firm to provide the service.
The professional reputation of firm, and satisfaction of current and/or prior clients.
The two shortlisted consultants for the Category 1 - Office Engineering are:
Biggs Cardosa Associates, Inc. of Oakland, California
Moffat & Nichol, of Walnut Creek, California
Public Works staff has identified the team led by Biggs Cardosa Associates as the most qualified team to provide the design services for the Dry Creek Road Bridge (21C0056) Replacement Project, BRLO 5921(061), RDS 15-22. Biggs Cardosa Associates is not a local vendor.
It is anticipated that preliminary engineering costs will occur in Fiscal Year 2016-17, FY 2017-18 and Fiscal Year 2018-19. Construction is anticipated to occur in Fiscal Year 2019-20. After completion of the preliminary engineering phase, CEQA/NEPA clearance and final design, staff will submit a request for authorization for the construction phase funds. All other future impact is limited to routine road maintenance as is currently performed.