- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- Yes
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- The required design modifications are necessary so that the project is constructed to meet the programmatic needs of the selected operator of the Crisis Stabilization Center. The operator was not in place during the early stages of the project, so their input was not available during the original design. While the original design meets Code, HHSA believes incorporating the input will result in an improved program, and therefore believes the cost of design modifications is warranted.
- Is the General Fund Affected
- No
- Future Fiscal Impact?
- No future fiscal impact is anticipated. The construction project is scheduled to be completed in the spring of 2017.
- Consequences if not approved
- If not approved, Public Works will not be able to proceed with design modifications and construction of the project that meets the programmatic requirements.
- Additional Information
- Costs for this amendment are anticipated to be covered by project contingencies within the current project budget.
Budget for the project is $2,286,963. Grant funds in the amount of $1,998,183 from the California Health Facilities Finance Authority have been secured and will be used for the construction/renovation of the CSS site, purchase of furnishings and equipment, and for information technology costs. Additional funds will be funded by HHSA Mental Health as discussed below.
A recent change in accounting procedures requires that each project maintain a positive cash balance on a project by project basis rather than on a fund basis. Therefore, an additional $800,000 has been made available for the project from the HHSA Mental Health Budget in order to cover the portion of the project not funded by the grant ($288,780). The remainder ($511,220), which is not considered to be part of the project budget, is provided to maintain a positive cash flow for the project. This additional funding for cash flow is needed because grant funds are only received on a reimbursement basis (i.e. the project would be cash flow negative after the County paid a contractor invoice up until the time we receive reimbursement of grant monies). Funds will be transferred to the project on an as needed basis for cash flow and will be returned to HHSA upon full receipt of grant funding and completion of the project.