Subject
2014 Earthquake Status as of June 30, 2017

Recommendation

Auditor-Controller to provide an overview of the 2014 Earthquake expenditures and revenues estimated through June 30, 2017 and requests authorization to complete the following accounting entries once the year is closed:

  1. Close out all projects in Division 10580, Subdivision 10580-01, where emergency work is completed;
  2. Increase the assignment in the General Fund fund balance for earthquake costs in the amount of $1,700,000 to $1,951,717 and rename it 2014 EQ FEMA Settlement;
  3. Carry forward final June 30, 2017 budget appropriations and related revenue for active projects associated with the Hall of Justice and Historic Courthouse.

 

Summary

Following the August 24, 2014 South Napa Earthquake, Subdivision 10580-01 was created within the Declared Emergency Division of the General Fund to track all revenue and expenditures related to the event.  The subdivision and all its related projects remained open through the current fiscal year.  As of June 30, 2017, all projects with the exception of the Hall of Justice and the Historic Courthouse are completed in regards to emergency work which is covered by the declared emergency.  

The Auditor-Controller will provide an overview of the status of all the projects created for this emergency event, broken out in four areas:

  1. Damaged buildings that are covered by Earthquake Insurance;
  2. Damaged buildings where Earthquake Insurance did not apply;
  3. Damaged roads, culverts and bridges; and
  4. Other costs associated with the Earthquake.

PROCEDURAL REQUIREMENTS

  1. Staff Report
  2. Motion, second and vote on item.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
General Fund and reimbursements from Insurance Proceeds.
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The remaining active projects in both the Hall of Justice and the Historic Courthouse resulting from the 2014 Earthquake are currently in design or under construction.  The impact of this item increases the budget appropriations and related contracts associated with the projects to fiscal year 2017-18 for the continuation and completion of the projects.
Is the General Fund Affected
Yes
Future Fiscal Impact?
After all invoices for fiscal year 2016-17 are processed, the budget for fiscal year 2017-18 will be adjusted (increased) by the remaining appropriations for each project. The Auditor-Controller will restrict FEMA reimbursements for possible deobligation in future budgets.
Consequences if not approved
The construction on the two buildings will not have the appropriation authority to continue paying the contractors.

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

Background

Following the August 24, 2014 South Napa Earthquake, Subdivision 10580-01 was created within the Declared Emergency Division of the General Fund to track all revenue and expenditures related to the event.  Although most activity occurred in fiscal year 2014-15, the subdivision and all its related projects remained open through the current fiscal year. As of June 30, 2017, all projects with the exception of the Hall of Justice and Historic Courthouse are completed in regards to emergency work which is covered by the declared emergency.

The Auditor-Controller will provide an overview of the status of all the projects created for this emergency event, broken out in four areas:

  1. Damaged buildings that are covered by Earthquake Insurance;
  2. Damaged buildings where Earthquake Insurance did not apply;
  3. Damaged roads, culverts and bridges; and
  4. Other costs associated with the Earthquake.

Total Expenditures to Date
To date, Napa County has paid out approximately $24.4 million dollars in response to the earthquake. This total cost includes everything from the initial County building clean up, contents replacement and tenant relocation to consultant costs, inmate relocation, and emergency road repairs.  This cost not include the cost of the Historic Courthouse reconstruction.  It should be noted that these numbers are not final as we will continue to pay expenses incurred in fiscal year 2017-18, however the additions are anticipated to be minimal with the exception of the active construction projects. Attached are detailed listings of each project and the total costs associated with each. 

Insurance
The County had insurance coverage for earthquake damage on four of its buildings and has so far received approximately $14.5 million to offset $21.9 million of expenses incurred on those buildings.  The County has also received $5.4 million for advances on the reconstruction of the Hall of Justice and Historic Courthouse which will be realized in fiscal year 2017-18.  The insurance deductible portion for the County on those four buildings is approximately $2.9 million, of which the County is anticipating FEMA/CalOES reimbursement of approximately $2.2 million.  Approximately $4.5 million of expenditures to date are either a) not covered under our insurance policy because they are deemed improvements or they are prorated to cover a portion of the cost, or b) they are still subject to discussion and clarification by insurance.  Our Risk Manager Kerry Whitney will continue to work with the insurance provider to ensure all agreeable costs are recovered.

Federal and State Emergency Funding
With expenditures of approximately $21.9 million on the insured buildings, the remaining $2.5 million comprises of the other buildings, road repairs and emergency response projects.  To date, Napa County has received $1,951,717 in Federal and State Emergency Funding (FEMA and CalOES).  The detailed pages indicate the projects for which the FEMA and CalOES funds were received, noted with an asterisk after the project number.  All of the receipts, with the exception of $218,751 for the project E9000-Napa EOC/ROC on page 6, are considered advances based on estimated project costs submitted by our Public Works engineers.  The complexity of the Federal and State emergency funding process is such that the County may not have final close out of these projects for over a year after completion with a final audit possibly as long as 10 years after ALL project close outs are completed.  Therefore, these advanced funds provide some cash flow but are not guaranteed to remain with the County.  Until the Federal and State audit requirement is satisfied, it is the recommendation of the Auditor-Controller to segregate and restrict these funds in a 2014 EQ FEMA Settlement assignment of fund balance at the end of each fiscal year.  The $218,751 mentioned as the exception, is a reimbursement for a submitted claim on actual dollars spent, not an advance on an estimated project cost.  However, it is still subject to a full audit and falls in the same non-guarantee category.

Impact to the General Fund
Due to the expertise and diligence of the County's Risk Manager Kerry Whitney, at this time, we have recovered all but approximately $7.4 million from the four buildings which sustained major damage (not assuming FEMA's $2.2 million recovery of our insurance deductibles or any pending costs subject to insurance discussions).  On the other buildings, the County has incurred approximately $532,000.  On our roads, bridges and culverts, the County has incurred approximately $929,000.  And finally, costs associated with the Emergency Operations Center (EOC), Recovery Operations Center (ROC), Administration, and Local Assistance Center (LAC) came to approximately $1.1 million.  Without factoring FEMA or CalOES, the County's out of pocket costs are just under $10 million. The current FEMA reimbursements, that have been obligated to the County, are approximately $5.6 million.  The County is anticipating additional obligations in the future.

Ongoing Monitoring of Federal and State Reimbursements
The Auditor-Controller has set up Project E9999 for tracking and maintaining of all receipts from FEMA and CalOES.  Once projects are fully audited by the regulatory agencies and a determination is made that the County has satisfied all requirements, Project E9999 will transfer the cash to the Non-Departmental revenue Division 10500, which will then release the assignment in the General Fund fund balance.  By using this methodology, the County ensures the funds are segregated, continuously monitored, and available if required to be refunded, through de-obligation, without impacting the General Fund in the future.

Requested Actions
The Auditor-Controller is requesting the authority to complete the following accounting entries once the year is closed:

  1. Close out all projects in Division 10580, Subdivision 10580-01 where emergency work is completed - this requires an intrafund transfer of cash to be moved into the project account to zero out the deficit in each project as of June 30, 2017. 
  2. Increase assignment of General Fund fund balance for earthquake costs in the amount of $1,700,000 to $1,951,717 and rename it 2014 EQ FEMA Settlement.  The original assignment was based on an estimate at the time the budget was initially prepared. 
  3. Carry forward budget appropriations and related revenue for active projects associated with the Hall of Justice and Historic Courthouse. Once final costs for the fiscal year are recorded, the remaining insurance advances will be realized in fiscal year 2017-18 and any remaining approved appropriations authority will be carried forward.  If additional appropriations are required, a budget adjustment will be brought to the Board in the future.