- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- No
- What is the revenue source?
- The immediate use of the TDA Grant is for the Devlin Road Segment E Project (RDS 11-06). Staff will be requesting to adjust the budget at the time the construction contract is awarded and the grant will be included as part of the revenue. The Devlin Road Segment E Project is funded by Traffic Mitigation Fee revenue and the TDA Grant will supplement the Project budget.
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- The use of CalRecycle grant funds will allow the Devlin Road Segment E Project to reduce the County funds necessary to complete the project and supports the environmentally preferred purchasing policy.
- Is the General Fund Affected
- No
- Future Fiscal Impact?
- Minor amount of future Roads funds are necessary for maintenance of the projects. Studies by CalRecycle show that the use of TDA as a fill material does not change the long term maintenance costs.
- Consequences if not approved
- The Devlin Road Segment E Project has been advertised to bidders, and, if the resolution is not approved, then the County will forfeit the grant funds and the project will have to be redesigned to eliminate the TDA fill.
- Additional Information
- It is estimated that approximately 400,000 fewer tires will be disposed of at landfills by using over 4,000 tons of TDA on the County projects.