The proposed project will repair pavement damage caused by the August 2014 South Napa Earthquake. The project was advertised for bid on February 8, 2019. Bids were opened on March 14, 2019 and eleven bids were received. The successful bidder is O.C. Jones & Sons, Inc. of Berkeley, California for their low base bid of $379,166. O.C. Jones & Sons, Inc. is not a local vendor. The Director of Public Works is recommending award to O.C. Jones & Sons, Inc. and requesting authorization for the Chair to sign the construction contract.
This item is consistent with the Strategic Plan goal to improve and maintain the existing transportation and roads system to safely accommodate all users.
- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- No
- What is the revenue source?
- The Board previously approved use of a $2.5 million General Fund loan to the Roads Fund to upfront the funds for the construction phase for the Earthquake Pavement Repair Project. Funds will be transferred from Roads Operations budget to the Roads CIP budgets - Fund 2040 - Subdivision 2040500 - Program R6351, R6350, R6407, R6402 and R6102.
The estimated project cost is $601,041. The Federal Highway Administration (FHWA) approved $779,932 for design and construction of permanent repairs based on early estimates of project cost. FHWA reimburses the County for 88.53% of allowable actual project costs. The County's local share is 11.47%. For Fiscal Year 2018-19, $91,077 was appropriated for these projects and there is a balance of $82,516 in the budget. Staff is requesting to increase the budget by $509,964 to construct the project. Caltrans has obligated FHWA funds for construction and County Staff will request reimbursements for allowable project costs once the projects are completed.
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- A construction contract must be awarded in order for the roads to be repaired and prevent further damage to the roadways.
- Is the General Fund Affected
- Yes
- Future Fiscal Impact?
- Construction will commence in Fiscal Year 2018-19 and the future fiscal impact will be limited to routine maintenance of the roads.
- Consequences if not approved
- The project will not proceed to the construction phase and further damage to the roadway could occur. Additionally, the County will have to return all federal funds received to date for the engineering phase.
- Additional Information
- It is anticipated that construction could continue into Fiscal Year 2019-20. The remaining balance of the budget at the end of Fiscal Year 2018-19 will be rolled over to Fiscal Year 2019-20 budget. Beyond construction, the future fiscal impact will be limited to routine maintenance of the roads.
Any reimbursement received from FHWA will be used for future earthquake projects. After all earthquake related projects are complete, FHWA reimbursements received plus any unspent portion of the $2.5M loan will be returned to the General Fund, which will satisfy the Roads commitment to repay the loan.
The five sites listed below were damaged in the August 2014 Napa earthquake. The extent of pavement restoration to repair the damage will range from crack sealing to the removal and replacement of pavement.
Repairs will be conducted at the following locations:
l DAF RAC-NAP-1 Oak Knoll Avenue Mile Post Marker 1.80 to 1.82
l DAF RAC-NAP-2 Oak Knoll Avenue Mile Post Marker 0.90 to 1.00
l DAF RAC-NAP-8 Old Sonoma Road Mile Post Marker 2.40 to 2.75
l DAF RAC-NAP-10 Old Sonoma Road Mile Post Marker 2.75 to 2.80
l DAF RAC-NAP-13 Cuttings Wharf Road Mile Post Marker 2.31 to 2.33
FHWA has approved $779,932 for design and construction of the permanent repairs at the five sites based upon original project estimates. We believe that is more than is necessary to complete the project, as the estimated total project cost is $601,041. FHWA will reimburse 88.53% of allowable actual project costs. The remaining 11.47% is the County's local share.
The 2014 Napa Earthquake Pavement Repairs Project was advertised for bid on February 8, 2019. Bids were opened on March 14, 2019 and eleven bids were received.
| O.C. Jones & Sons, Inc. |
Berkeley, CA |
$379,166.00 |
| Granite Construction |
Santa Rosa, CA |
$390,818.18 |
| Paving Construction Services, Inc. |
Aviso, CA |
$394,489.40 |
| Ghilotti Bros, Inc. |
San Rafael, CA |
$397,075.00 |
| Northwest Paving, Inc. |
Redding, CA |
$447,150.00 |
| Northern Pacific, Inc. |
Napa, CA |
$467,939.00 |
| G.D. Nielson Construction, Inc. |
Napa, CA |
$492,225.00 |
| Alaniz Construction, Inc. |
Fremont, CA |
$509,110.00 |
| Martin Brothers Construction, Inc. |
Sacramento, CA |
$516,682.15 |
| Team Ghilotti, Inc. |
Petaluma, CA |
$518,695.53 |
| J.A. Gonsalves & Son Construction |
Napa, CA |
$590,925.00 |
The engineer's estimate was $460,000. The successful bidder is O.C. Jones & Sons, Inc. for their low base bid of $379,166.
Construction is anticipated to commence in June 2019 and to be completed by end of summer, weather permitting. The project "soft costs" are approximately 27% of the total project costs, which is consistent with other non-complex road repair projects. A 15% contingency is requested for any unforeseen items of work.
O.C. Jones & Sons, Inc. is not a local vendor. Staff outreach to the local construction contractor community included advertising the request for bids in the Napa Valley Register and the Solano-Napa Builder's Exchange, and by posting on DBEGoodFaith.com and the County website. Staff also sent "Notices to Contractors" to the local construction community. Once the construction contract is awarded the County will contact the Napa County Workforce Investment Board (WIB) and will require the successful contractor to contact the WIB informing them of hiring needs.