Steven Lederer - Director of Public Works - Public Works
Report By
Steven Lederer - Director, Public Works - 259-8228
Agenda Date
Resolution / Ordinance
N
Category
ADMINISTRATIVE ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
2017 Winter Storm Projects; Possible Eligibility for FEMA Funding
Recommendation
Director of Public Works to provide an update on seven 2017 Winter Storm projects that may be eligible for partial FEMA funding.
Summary
The January and February Storms of 2017 resulted in significant damage to the County roads system. After the immediate storm cleanup, there were still 37 sites remaining with significant damage. For a variety of reasons the County determined that it was best to repair these sites over a multiple year period using local funds as they became available, as opposed to attempting to repair all of the areas concurrently under the FEMA process, which would have been virtually impossible given resource and financial constraints. Eighteen projects have since been completed, with 19 remaining. Of the 19, two are in construction and 8 are about to go into design. FEMA has shown an interest in providing partial funding for 7 of the remaining projects.
PROCEDURAL REQUIREMENTS
Staff reports.
Public comments.
Board may (if desired) provide input to staff.
Fiscal Impact
Is there a Fiscal Impact?
No
Impact
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.
Background
The January and February Storms of 2017 resulted in significant damage to the County roads system. After the immediate storm cleanup, there were 37 sites remaining with significant damage. Early estimates indicated repair costs would be in the range of $30 million to $50 million. On December 5, 2017, staff discussed, and the Board approved, a planning guide for long term roads funding (recognizing that actual budgetary decisions are made via the budget process on an annual basis). At that time staff requested FEMA to withdraw projects the County was not pursuing from FEMA funding consideration.
As documented in that December 5, 2017 agenda item, for a variety of reasons the County determined that it was best to repair these storm damaged sites over a multiple year period using local funds as they became available, as opposed to attempting to repair all of the areas concurrently under the FEMA process, which actually would have been more expensive, and would have been virtually impossible given resource and financial constraints.
The County has executed on its funding and timing plan, completing 18 projects so far. As we approached some of the remaining projects, FEMA has stated they might be willing to provide partial reimbursement for 7 of these projects. On April 10, 2018, your Board approved an agenda item to provide local design funding for 2 of the 7 projects, Ridgecrest Drive and Sunnyhill Drive, which included the understanding that FEMA might provide partial reimbursement for those two projects. On April 9, 2019, the Board subsequently approved the construction contracts for these two projects under same premise. FEMA may also provide partial reimbursement for the remaining 5 upcoming projects, specifically Mt. Veeder Rd. Mile Post Marker (MPM) 4.75, three locations on Dry Creek Road, (MPM 7.51, 7.75, and 10.5), and Berryessa Knoxville Road MPM 20.5-22. No other upcoming storm projects are expected to involve FEMA. The five projects may be reimbursed for a total of $3.625 Million as follows:
Mt. Veeder Road $1,289,395.67 (FEMA funding)
Dry Creek Road (MPM 7.51) $696,573.93 (FEMA funding)
Dry Creek Road (MPM 7.75) $240,503.24 (FEMA funding)
Dry Creek Road (MPM 10.5) $397,669.90 (FEMA funding)
At this stage, given that the seven projects listed above are already moving forward per the County's plan, the effort to obtain FEMA reimbursement will be significantly less than what we were facing back in 2017. Recognizing that even now FEMA funding would be uncertain, it still appears the efforts to pursue it are minimal enough to make pursuit of it, which could be in the range of $3.5 to $5 million (as referenced above), a worthwhile endeavor. Any funding received would be held by the Auditor until all audits are complete, and as such there is no risk should FEMA change it's mind later. As an added benefit, the FEMA audit period has recently been reduced to 3 years from 10 years, so this process will be determined more expeditiously than in the past. Any retained funding post audit would then be released to accomplish additional road repair projects.
For these reasons, staff is recommending moving ahead with the FEMA reimbursement process rather than withdrawing the request for FEMA funding as originally recommended in 2017. Staff welcomes Board input on the Storm recovery process.