Subject
2014 Napa Earthquake Structure Repairs, RDS 18-06 & RDS 18-07 - Approval of Plans and Specifications

Recommendation

Director of Public Works requests approval of plans and specifications for the 2014 Napa Earthquake Minor Structure Repairs listed below and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to section 20150.8 of the Public Contract Code:

  1. DAF RAC-NAP-20 Silverado Trail MPM 1.47, RDS 18-06 
  2. DAF RAC-NAP-24 Silverado Trail MPM 0.16, RDS 18-06 
  3. DAF RAC-NAP-25 Silverado Trail MPM 10.64, RDS 18-06
  4. DAF RAC-NAP-17 Old Sonoma Road MPM 2.27, RDS 18-07

Summary

In the August 2014 South Napa Earthquake, several county structures (bridges and culverts) sustained damage.  The subject sits sustained damage and the proposed project will repair the structures as follows:       

  • Silverado Trail MPM 1.47 - pressure grout cracks      
  • Silverado Trail MPM 0.16  - reinforce cracks with a concrete section      
  • Silverado Trail MPM 10.64  - pressure grout cracks     
  • Old Sonoma Road MPM 2.27 - pressure grout cracks inside the culvert barrel with a wire mesh

The sites qualified for Federal Highway Administration (FHWA) funding. The federal cost share is 88.53% and the local share is 11.47%.  FHWA, in the four Damage Assessment Forms (DAFs), has approved $823,150 for design and constructions of the projects.  FHWA has issued authorization for construction for the three Silverado Trail sites. Authorization for construction of the Old Sonoma Road site is in process, and approval is expected soon.  Advertisement of these projects is contingent upon receiving authorization for this last site.    

It is recommended that the Board approve the plans and specifications for the above sites and authorize the Director of Public Works to advertise for the sealed bids for construction. Project budgets are attached for reference.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
Roads Capital Improvement Project budgets - Fund 2040 - Subdivision 2040500 - Program R8300 (Old Sonoma Road MPM 2.27), R8350 (Silverado Trail MPM 0.16), R8360 (Silverado Trail MPM 1.47), and R8370 (Silverado Trail MPM 10.64).
 
The Board previously approved Roads Operations budget to upfront the funds for various projects from the 2014 earthquake including the $372,460 allocated for design of these four structural repair projects.

Once construction bids are received, staff will request additional funds to be made available from the $2.5 million dollar loan held in Roads Operations budget to cover the remaining expenses for construction, construction management, material testing, contingency, and County staff time. 

These structural repair projects are eligible for reimbursement from FHWA at 88.53%.  The County has already received authorization for $280,000 for preliminary engineering ($150,000 for Old Sonoma Road, $130,000 for Silverado Trail 0.16, 1.47, 10.64) and $203,150 for construction and construction engineering for Silverado Trail 0.16, 1.47, 10.64 .  Additionally, we have requested $340,000 for the construction and construction engineering for Old Sonoma Road.  The total cost of the projects is estimated to be $823,150 with FHWA reimbursement of 88.53% ($728,734) and County cost share of 11.47% ($94,416).  

The County must receive authorization from FHWA for the construction funds prior to advertising.  

In Fiscal Year 2017-18, $372,460 was appropriated for these projects, $20,527 has been spent leaving a balance of $351,933 in the budget. Staff will return to request additional funds with the award of a construction contract.  
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Approval of plans and specifications and authorization to advertise for bids is necessary to move the project forward toward construction.
Is the General Fund Affected
No
Future Fiscal Impact?
Construction will commence in Fiscal Year 2019-20. The remaining balance of the budget at the end of Fiscal Year 2018-19 will be rolled over to Fiscal Year 2019-20 budget. The future fiscal impact will be limited to routine maintenance of the structures.
Consequences if not approved
If the Board does not authorize the project to be advertised for sealed bids, then the County will not meet the FHWA deadline to complete the project, and the County will forfeit the FHWA funding and will have to return all funds received for the design phase.
Additional Information
At the completion of all FHWA funded earthquake projects, the $2.5M loan, minus the County costs for these projects, will be returned to the General Fund the and the loan will be considered closed and satisfied at that time.  We expect this to occur in Fiscal Year 2020-21, a year earlier than originally expected. 

Impact

Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that these projects do not have a significant effect on the environment and are exempt from the California Environmental Quality Act. [See Class 1 ("Existing Facilities") which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR 15301; see also Napa County's Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]  The CEQA determination for these projects have been filed with the recorders office.  Caltrans has determined that these projects qualify for a categorical exclusion under the National Environmental Policy Act.

Background

In the August 2014 South Napa Earthquake several county structures (bridges and culverts) sustained damage. With the recent completion of 5 FHWA funded roads project, and the expected completion of the projects included in this agenda item, the County will only have four FHWA funded projects left to complete from the 2014 earthquake. It is expected that all can be completed this fiscal year and next.
 
There are an additional six outstanding FEMA funded roads related earthquake projects to complete, including two on Third Ave., two on Whitehall Lane, one on Manley Lane, and the Partrick Road Bridge.