Submitter

Director
Steven Lederer - Director of Public Works - Public Works
Report By
Mallika Ramachandran - Engineering Manager - 259-8194
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
2017 Storm Damage Repairs on Dry Creek Road and Mount Veeder Road - Approval of Plans and Specifications

Recommendation

Director of Public Works requests approval of plans and specifications and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code for the following projects:

  1. Dry Creek Road - MPM 7.51- 4305 NANCC53, RDS 19-15
  2. Dry Creek Road - MPM 7.75 - 4308 NANCC94, RDS 19-10
  3. Dry Creek Road - MPM 10.5 - 4308 NANCC93, RDS 19-09
  4. Mt. Veeder Road - MPM 4.75 - 4308 NANCC97, RDS 19-11

Summary

During the January 2017 storm event, the subject sites sustained significant damage as follows:

  • Dry Creek Road - MPM 7.51- Sustained 180 feet of road and embankment failure. 
  • Dry Creek Road - MPM 7.75 - Sustained 120 feet of road and embankment failure. 
  • Dry Creek Road - MPM 10.5 - Sustained 100 feet of road and embankment failure. 
  • Mt. Veeder Road - MPM 4.75 - Sustained 330 feet of road failure.

For each, the proposed repair is to reconstruct the road with a steel soldier pile concrete retaining wall.  The above four sites qualified for federal funding and the Federal Emergency Management Agency (FEMA) has obligated funds and granted time extensions to October 2019 for these projects. The federal match for these projects are 75% FEMA, 18.75% California Office of Emergency Services (Cal OES) and 6.25% local match. FEMA has identified funding for these four projects as listed below. However, current project budget estimates (attached) are above what FEMA has identified and since these are large projects, staff anticipates that FEMA will ultimately approve the actual cost incurred for the design and construction of these projects. 

  • Dry Creek Road - MPM 7.51 - $695,573
  • Dry Creek Road - MPM 7.75 - $240,503
  • Dry Creek Road - MPM 10.5 - $397,669
  • Mt. Veeder Road - MPM 4.75 -$1,289,395

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
The Roads Fund 2040, Capital Improvement Projects Sub­division 2040500.  The current design phase board appropriations in the respective program is:

S7202 Dry Creek Road - MPM 7.51  -  $155,300
S7402 Dry Creek Road - MPM 7.75  -  $139,550
S7313 Dry Creek Road - MPM 10.5  -  $137,250
S7405 Mt. Veeder Road - MPM 4.75 -  $168,300 

Each program has received $39,000 from the Roads Operations Fund (a total of $156,000). The additional $444,400 of funding has come from Measure T.

These four sites qualified for federal funding and the Federal Emergency Management Agency (FEMA) has obligated funds and granted time extensions to October 2019 for these projects. The federal match for these projects are 75% FEMA, 18.75% California Office of Emergency Services (Cal OES) and 6.25% local match. FEMA has currently identified funding for these four projects as listed in the Executive Summary, but since these are large projects, staff anticipates that FEMA will ultimately approve the actual cost incurred for the design and construction of these projects.  The full cost of each project is estimated as follows:

Dry Creek Road - MPM 7.51 - $1,029,300
Dry Creek Road - MPM 7.75 - $806,650
Dry Creek Road - MPM 10.5 - $804,250 
Mt. Veeder Road - MPM 4.75 - $1,421,800 

Construction funds have not been appropriated. Staff will request construction phase budgets after bids are opened and when a construction contract award is requested.

Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
FEMA has obligated funds and granted time extensions to October 2019 to complete these four identified FEMA projects. If not completed (or new extensions granted), the County could forfeit approximately $2,623,140 of FEMA funding.
Is the General Fund Affected
No
Future Fiscal Impact?
These projects are expected to be complete in fiscal year 2019-20.
Consequences if not approved
FEMA has obligated funds and granted time extensions to October 2019 to complete the four identified FEMA projects. If not completed, the County could forfeit approximately $2,623,140 of FEMA funding. 

Additional Information
Before the County was aware that significant funding was available for these projects from FEMA, the projects were included in the 5 year plan for Measure T.  Therefore, Measure T funds, once appropriated by the Board, will provide the cash flow for these projects.  When FEMA reimbursement is received, the funds must be returned to the Measure T account for use on future road projects.  While the Auditor Controller is holding most FEMA reimbursements for many years in the anticipation of a possible negative audit and "claw back" of funds, that should not be the case with these funds.  In the unlikely event that FEMA were to try and take these funds back some years in the future, the difference would be made up with future Measure T disbursements, which will continue to come in for 24 more years.   

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.  The projects qualify for categorical exemptions under CEQA. FEMA has determined that the projects qualify for a categorical exclusions under the National Environmental Policy.

Background

This agenda item requests permission to go "out to bid" to engage a contractor to repair 4 sites that sustained significant damage in the 2017 storms.  The sites are Dry Creek Road - MPM 7.51, Dry Creek Road - MPM 7.75, Dry Creek Road - MPM 10.5, and Mt. Veeder Road MPM 4.75.  In all cases the roads sustained significant slippage, resulting in current or impending lane failures. The proposed repair is to reconstruct the roads with a steel soldier pile concrete retaining wall.

Weather permitting, these projects can move into construction phase in FY 2019-20 (most likely this fall). It is recommended that the Board approve the plans and specifications for the above sites and authorize the Director of Public Works to advertise for the sealed bids for construction.  Staff intends to ask the Board to award construction contracts at its August 20th meeting.