- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- No
- What is the revenue source?
- The Roads Fund 2040, Capital Improvement Projects Subdivision 2040500. The current design phase board appropriations in the respective program is:
S7202 Dry Creek Road - MPM 7.51 - $155,300
S7402 Dry Creek Road - MPM 7.75 - $139,550
S7313 Dry Creek Road - MPM 10.5 - $137,250
S7405 Mt. Veeder Road - MPM 4.75 - $168,300
Each program has received $39,000 from the Roads Operations Fund (a total of $156,000). The additional $444,400 of funding has come from Measure T.
These four sites qualified for federal funding and the Federal Emergency Management Agency (FEMA) has obligated funds and granted time extensions to October 2019 for these projects. The federal match for these projects are 75% FEMA, 18.75% California Office of Emergency Services (Cal OES) and 6.25% local match. FEMA has currently identified funding for these four projects as listed in the Executive Summary, but since these are large projects, staff anticipates that FEMA will ultimately approve the actual cost incurred for the design and construction of these projects. The full cost of each project is estimated as follows:
Dry Creek Road - MPM 7.51 - $1,029,300
Dry Creek Road - MPM 7.75 - $806,650
Dry Creek Road - MPM 10.5 - $804,250
Mt. Veeder Road - MPM 4.75 - $1,421,800
Construction funds have not been appropriated. Staff will request construction phase budgets after bids are opened and when a construction contract award is requested.
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- FEMA has obligated funds and granted time extensions to October 2019 to complete these four identified FEMA projects. If not completed (or new extensions granted), the County could forfeit approximately $2,623,140 of FEMA funding.
- Is the General Fund Affected
- No
- Future Fiscal Impact?
- These projects are expected to be complete in fiscal year 2019-20.
- Consequences if not approved
- FEMA has obligated funds and granted time extensions to October 2019 to complete the four identified FEMA projects. If not completed, the County could forfeit approximately $2,623,140 of FEMA funding.
- Additional Information
- Before the County was aware that significant funding was available for these projects from FEMA, the projects were included in the 5 year plan for Measure T. Therefore, Measure T funds, once appropriated by the Board, will provide the cash flow for these projects. When FEMA reimbursement is received, the funds must be returned to the Measure T account for use on future road projects. While the Auditor Controller is holding most FEMA reimbursements for many years in the anticipation of a possible negative audit and "claw back" of funds, that should not be the case with these funds. In the unlikely event that FEMA were to try and take these funds back some years in the future, the difference would be made up with future Measure T disbursements, which will continue to come in for 24 more years.