Submitter

Director
Steven Lederer - Director of Public Works - Public Works
Report By
Graham Wadsworth - Engineering Supervisor - 259-8331
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
2014 Earthquake Pavement Repairs, RDS 18-14 - Approval of Contract Change Orders

Recommendation

Director of Public Works requests the following:

  1. Approval of and authorization for the Director of Public Works to sign contract change orders to the 2014 Earthquake Pavement, RDS 18-14, construction contract with O. C. Jones and Sons, Inc. for a maximum not to exceed amount of $125,000 to respond to unexpected circumstances during construction at Old Sonoma Road (DAF 8) and Cutting Wharf Road (DAF 13) (2/3 vote required);
  2. Board adoption of the findings expanded upon in this Board item; namely that changed conditions exist and public bidding would not produce an advantage and would be inappropriate, impractical, and not in the County's best interest due to the circumstances discussed in this Board item; and 
  3. Approval of Budget Transfer No. DPW003 for the following (4/5 vote required):
    1. Increase appropriation by $125,000 in the Roads Operations budget (Fund 2040, Sub-Division 2040000) offset by the use of a portion of the $2.5 million loan from the General Fund to the Roads Operations;
    2. Increase appropriation by $100,000 in Program R6407, DAF 8 - Old Sonoma Road MPM 2.07 in the Roads CIP Budget (Fund 2040, Subdivision 2040500) offset by increase in revenue from the transfer from the Roads Operations budget; and
    3. Increase appropriation by $25,000 in Program R6102, DAF 13 - Cuttings Wharf Road MPM 2.31 in the Roads CIP Budget (Fund 2040, Subdivision 2040500) offset by increase in revenue from the transfer from the Roads Operations budget.

Summary

On May 14, 2019, the Board of Supervisors awarded a construction contract to O.C. Jones & Sons, Inc. of Berkeley, California for the repairs of pavement at 5 sites damaged in the August 2014 South Napa Earthquake. The repairs are 90% complete, but contract change orders are necessary to complete unexpected work at Old Sonoma Road (DAF 8) and Cuttings Wharf Road (DAF 13). The existing budget for all 5 projects is $600,435, the total expenditures to date are $387,413, and the proposed budget including the following requested change orders is $725,435. The program budgets are attached for reference.  

The request for approval of the change orders are for the following sites to address the specified unforeseen circumstances:

  • DAF 8 - Old Sonoma Road: encountered unforeseen soft soil conditions requiring removal and replacement with pulverized pavement material ($40,000) and to replace high friction surface treatment ($60,000)
  • DAF 13 - Cuttings Wharf Road: encountered settlement due to soft subgrade requiring additional hot mixed asphalt concrete overlay to bring the road to grade ($25,000)

Due to site safety, a portion of the work at DAF 8 - Old Sonoma Road has been completed to remove soft soil and replace it with pulverized pavement. The remaining work is pending approval of the budget increase and approval of the contract change orders. This work is necessary to increase safety to the public.

The items listed in these change orders are necessary due to unforeseen site conditions that have been encountered during construction. Competitive bidding at this point in time would not produce an advantage in this instance because O. C. Jones and Sons is currently onsite and familiar with the existing site conditions which will keep overall project costs down. Due to safety concerns, advertisement for competitive bids would be undesirable, impractical, or impossible.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
On May 14, 2019, the Board transferred $509,964 from Roads Operations budget, by the use of a portion of the $2.5 million loan from the General Fund to the Roads Operations, to the Roads CIP budgets - Fund 2040 - Subdivision 2040500 - Program R6351, R6350, R6407, R6402 and R6102 to upfront the cost of construction.  On June 18, 2019, the Board approved revision to the budget for different programs with no net change to the total budget. Board appropriation to date for the programs is $600,435. With approval of todays request, the total budget for the programs will increase by $125,000, for a new total of $725,435. The project is approximately 90% complete.  It is estimated that approximately $40,000 of the existing $56,875 contingency budget is needed to pay for actual quantities of materials placed at each site.

Staff is requesting to increase the budget by $125,000 from a transfer of said amount from the Roads Operations budget for the contract change orders and will request reimbursements from FHWA for allowable project costs once the projects are completed. The Federal Highway Administration (FHWA) approved $779,932 for design and construction of permanent repairs based on early estimates of project cost. FHWA reimburses the County for 88.53% of allowable actual project costs. The County's local share is 11.47%.
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
The Program R6407 - DAF 8 at Old Sonoma Road and Program R6102 - DAF 13 at Cuttings Wharf Road do not have adequate contingency budget to address the required, unexpected work.
Is the General Fund Affected
Yes
Future Fiscal Impact?
The future fiscal impact will be limited to routine maintenance of the five sites.
Consequences if not approved
If the budget transfer is not approved, then the necessary work to increase safety to the public cannot be completed.
Additional Information
Livable Economy for All

Impact

ENVIRONMENTAL DETERMINATION: Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.] Caltrans has determined that the project qualifies for a categorical exclusion under the National Environmental Policy Act.

Background

On May 14, 2019, the Board of Supervisors awarded a construction contract to O.C. Jones & Sons, Inc. for their low base bid of $379,166 for pavement repairs at the five sites listed below. Construction commenced in June 2019 and should be completed in September, 2019, weather permitting.

  • DAF RAC-NAP-1     Oak Knoll Avenue Mile Post Marker 1.80 to 1.82     
  • DAF RAC-NAP-2     Oak Knoll Avenue Mile Post Marker 0.90 to 1.00     
  • DAF RAC-NAP-8     Old Sonoma Road Mile Post Marker 2.40 to 2.75    
  • DAF RAC-NAP-10   Old Sonoma Road Mile Post Marker 2.75 to 2.80     
  • DAF RAC-NAP-13   Cuttings Wharf Road Mile Post Marker 2.31 to 2.33  

FHWA has approved $779,932 for design and construction of the permanent repairs at the five sites based upon original project estimates. The total proposed project cost, including the requested change orders, is now $725,435, so there is adequate federal funding for the contract change orders. FHWA will reimburse 88.53% of allowable actual project costs. The remaining 11.47% is the County's local share.  

The repairs are 90% complete and approval of contract change orders are necessary to complete the unexpected work at Old Sonoma Road (DAF 8) and Cuttings Wharf Road (DAF 13).

The change orders exceed the Director's delegated authority as the aggregate change will exceed 25% of the original contract amount and accordingly need Board authorization. The two change orders related to Old Sonoma Road additionally require the Board to make the following findings: (1) competitive bidding would not produce an advantage, and (2) competitive bidding would be undesirable, impractical, or impossible.

In this instance, competitive bidding would not produce an advantage because O. C. Jones and Sons is currently onsite and familiar with the existing site conditions, thereby avoiding mobilization costs and significant delays that would result from bidding the change orders. When the existing road was pulverized, the high friction surface treatment (HFST) that was placed with Highway Safety Improvement Program grant funding was removed. The HFST was effective in reducing accidents at the intersection and it should be replaced as soon as possible. When Cuttings Wharf Road was paved, the full thickness of asphalt concrete was not replaced in order to minimize the amount of new asphalt that might need to be removed, so there is a dip in the road that should be remedied as soon as possible to prevent potential damage to vehicles. Due to safety concerns, advertisement for competitive bids would be undesirable, impractical, or impossible.

The Director of Public Works is requesting a budget increase in Programs R6407 DAF 8 - Old Sonoma Road and R6102 DAF 13 Cuttings Wharf Road; recommends contract change orders to remove unsuitable soft soil ($40,000), replace high friction surface treatment ($60,000) on Old Sonoma Road, and overlay Cuttings Wharf Road ($25,000); and is requesting authorization for the Director of Public Works to sign the change orders for the maximum not to exceed amount of $125,000 to O. C. Jones & Sons, Inc.