Partrick Road Bridge at Mile Post Marker (MPM) 0.88 sustained substantial damage in the August 24, 2014 Napa Earthquake. The bridge qualified for Federal Emergency Management Agency (FEMA) funding. On August 24, 2015, FEMA obligated $14,270 in Project Worksheet (PW) 66 to pressure grout the visible cracks in the bridge structure. In the County’s opinion, the scope of work and the funding approved by FEMA was insufficient to restore the bridge to its pre-disaster load carrying capacity. Napa County submitted an appeal (First Appeal) on October 21, 2015, which was denied by FEMA on February 2, 2018. The County filed a second appeal on April 5, 2019, and on June 20, 2019, FEMA approved the second appeal and agreed to fund the project at a more appropriate level.
Since 2014, Biggs Cardosa Associates, Inc (BCA) as part of a consulting engineering team lead by WRECO, has been assisting the County with various earthquake projects including the Partrick Road Bridge, MPM 0.88 (LOP 198) and the two Whitehall Lane Bridges (LOP 217 and LOP 218). These are the three remaining FEMA funded earthquake repair projects to be designed and constructed. These are complex projects relating to repairs to stone bridges and the County requires the support of WRECO’s team to complete these projects. Approval of Amendment No. 2 to Agreement No.170638 is necessary for WRECO's team to provide continuous engineering support for the earthquake projects. The proposed amendment extends the term of the agreement and does not change maximum compensation, which is $150,000 per fiscal year.
- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- No
- What is the revenue source?
- FEMA has not yet fully obligated the funds for this project. Staff is requesting $50,000 funding from the Accumulate Capital Outlay Fund to start preliminary engineering and to coordinate the required scope of work and budget with FEMA and California Governor’s Office of Emergency Services (Cal OES). Staff will request reimbursements from FEMA once the budget is obligated by FEMA. The federal match for these projects are typically 75% FEMA, 18.75% California Office of Emergency Services (Cal OES) and 6.25% local match.
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- If not approved, the coordination with FEMA and Cal OES to develop the Project Worksheet cannot continue and funding will not be obligated to repair the bridge. The County installed a temporary Bailey bridge in November 2014 as an emergency protective measure to provide ingress/egress to properties west of the bridge. Typically a new bridge has a useful life of 75 years and can be extended with regular maintenance. A temporary structure is assumed to have a life of 10 years. Every ten years, temporary bridge parts need to be replaced in their entirety and it will cost the County significant funds to keep the Bailey bridge in place for an extended period. Furthermore, repairs to the Bailey Bridge would require road closures and cause disruptions to the public. To maintain the Bailey Bridge in place for a long period is not standard engineering practice or cost effective. The Bailey bridge is a temporary bridge and should be replaced with a permanent bridge.
- Is the General Fund Affected
- No
- Future Fiscal Impact?
- Staff will return to the Board for authorization of design and construction funds. Design, Environmental Clearance, and Permitting is anticipated to be in FY 2019-20 and FY2021-22. Construction is anticipated to be in Fiscal Year 2022-23. Future fiscal impacts are routine maintenance of the road and bridge.
- Consequences if not approved
- If not approved, coordination with FEMA and Cal OES to develop the Project Worksheet cannot continue and funding will not be obligated to build the bridge.
- County Strategic Plan Pillar Addressed
- Livable Economy for All - Improve and maintain the existing transportation and roads system to safely accommodate all users.
- Additional Information
- While the project will be partially reimbursed by FEMA and Cal OES, there will be a need to decide where advance funds will come from for construction. Roads Operations does not have a large enough fund balance to advance funds. Public Works will work with the CEO and return to the Board at a later date with a recommendations. The preference is to identify general fund resources to meet the need for advance funds. If general fund is unavailable, an alternate fund source will need to be identified.
Partrick Road Bridge at MPM 0.88 sustained substantial damage in the August 24, 2014 Napa Earthquake. The bridge was originally built in the early 1900's as a stone arch bridge and was modified around 1920-1950 to a reinforced concrete bridge seated on the original stone masonry abutment and foundation. Partrick Road is a dead-end roadway and the bridge provides the only access to approximately 30 properties west of the bridge. There are vineyard businesses west of the bridge and heavy trucks cross the bridge. The bridge qualified for Federal Emergency Management Agency (FEMA) funding. Initially, a load and speed restriction was posted on the bridge after the earthquake and the bridge was monitored. The bridge continued to shift and after consultation with FEMA, the County installed a temporary Bailey bridge on November 25, 2014 as an emergency protective measure. Installation of the Bailey bridge that spans over the existing bridge is, for the moment, providing ingress/egress to properties west of the bridge.
The County’s Engineering Manager for Roads and BCA’s Structural Engineer inspected the bridge and documented the damages on several occasions after the disaster, developed repair solutions, engineering estimates, and reports and submitted them to FEMA and California Governor’s Office of Emergency Services (Cal OES). Staff and consultant also participated in several FEMA and Cal OES damage assessment site visits. Nonetheless, on August 24, 2015, FEMA obligated only $14,270 in Project Worksheet (PW) 66 which provided funds only to pressure grout the visible cracks. In the County’s opinion the scope of work and the funding was insufficient to restore the bridge to its pre-disaster load-carrying capacity. The bridge restoration must meet current seismic codes, American Association of Highway and Transportation Officials (AASHTO) Load and Resistance Factor Design (LFRD) standards, and safety and regulatory requirements. The County submitted an appeal (First appeal) on October 21, 2015 outlining the required scope of work and the cost to restore the bridge. An evaluation of repair versus replacement option was also presented in the appeal.
On April 19, 2016, representatives from FEMA and Cal OES met with County staff to discuss the First Appeal. Pursuant to this meeting FEMA implemented a task force consisting of a FEMA Appeal Analyst, the County’s Engineering Manager, BCA and Cal OES to perform forensic investigation on the bridge and to develop a repair solution. The task force met in May and June 2016, performed site visits, and reviewed all historical data and the damages sustained by the bridge. Several reports supporting the County’s scope and estimated cost for repair or replacement were prepared and submitted to the FEMA Appeal Analyst. After the submittal of all requested documents, follow-up on the appeal continued through 2018.
On February 5, 2018, the County received Cal OES’s February 2, 2018 letter transmitting FEMA’s denial of the First appeal. In their denial, the Regional Administrator claimed that (1) the documentation provided by the County did not establish the pre-disaster condition of the bridge, (2) the County failed to show how and to what extent the post-disaster condition of the bridge is distinguishable from the pre-disaster condition of the bridge, and (3) the County failed to establish that the claimed damage was a result of the disaster as required by Title 44 of the Code of Federal Regulations (44 CFR) section 206.223(a)(1). The letter provided that the County could pursue a second and final appeal, if desired, which had to be submitted to Cal OES within 60 days from the date of the letter, which was April 5, 2018.
The County disagreed with FEMA’s determination and filed a second appeal on April 5, 2018. In the second appeal, the County addressed all of the above reasons for FEMA’s denial of the first appeal. The second appeal requested FEMA overturn the findings from the First Appeal and obligate an additional $2,058,670, which would result in a total obligation of $2,072,940 ($1,124,212 for bridge replacement, $246,729 for the Bailey bridge and wingwall repairs, $497,200 for related engineering, right of way and environmental, and $204,800 construction management/inspection). The County proposed bridge replacement versus repair because it was more cost effective and had the maximum benefit.
On June 20, 2019, Cal OES sent a letter informing the County that FEMA, after reviewing the second appeal, had determined the Patrick Road Bridge sustained significant structural damage as a direct result of the disaster. FEMA Headquarters directed FEMA Region IX and Cal OES to work with the County to develop an appropriate scope of work and eligible costs including costs for required codes and standards upgrades. On August 27, 2019, FEMA and Cal OES met with the County to discuss the project and requested the County submit the actual costs for the Bailey bridge and updated cost estimates for the permanent project (replace and repair options). The requested information and the updated cost estimates for the Bailey Bridge and permanent repair (2019 cost) have been submitted to Cal OES and FEMA.
The cost of the Bailey Bridge to date is $171,780 (construction, engineering, environmental clearance, permitting and maintenance). The probable project budget for the permanent repair of Partrick Road Bridge is $2,690,845 (2019 cost). The estimated construction cost with 15% contingency is $1,529,845. The estimated design, environmental and permitting cost is $561,000 (with 10% contingency); construction management, inspection and material testing cost is $440,000 (with 10% contingency); County project management cost is $121,000 (with 10% contingency). Other project related costs (Permits, Advertisement, Printing, Postage, TCE, County Sheriff, Language Translation, etc.) is $39,000. FEMA has not obligated the funds for this project.
In December 2013, the County issued a Request for Proposal (RFP) and WRECO was shortlisted on January 28, 2014 to provide services for future county projects. The RFP specified that the list of shortlisted consultants will be maintained in the County’s database for five years and may be asked to submit a proposal for various projects. The August 24, 2014 earthquake caused structural damages to many county facilities. The imminent danger to the public required structural engineers to perform damage assessments of county‘s culverts and bridges. On September 19, 2014, the Purchasing Agent with delegated authority from the Board awarded a contract to WRECO to provide on-call engineering, inspection, environmental and other miscellaneous engineering services, including staff augmentation to address work in relation to the South Napa Earthquake that occurred on August 24, 2014. On May 9th 2017, the Board approved Amendment No.1 to the Agreement to extend the original term of the agreement by three additional years to June 30, 2020.
Staff and consultant efforts are necessary to continue to coordinate with FEMA and Cal OES and to develop the scope and probable project cost for the revised Project Worksheet and obligation of FEMA funds. Since 2014, BCA (structural engineer), as a part of the WRECO's team, has been assisting the County with various earthquake projects including the Partrick Road Bridge, MPM 0.88 (LOP 198) and the two Whitehall Lane Bridges (LOP 217 and LOP 218). These are the three remaining FEMA earthquake repair projects to be designed and constructed. These are complex projects relating to repairs to stone bridges and the County requires the support of WRECO’s team to complete these projects.
Approval of Amendment No. 2 to Agreement No. 170638 extending the term of the agreement to June 30, 2025 for a contract amount of $150,000 per fiscal year is necessary for WRECO's team to provide continuous engineering support for the earthquake projects.