- What is the revenue source?
- The Roads Fund 2040, Capital Improvement Projects Subdivision 2040500. The estimated total project cost for these four projects is $4,445,897 with $600,400 already transferred to the four projects and the remaining $3,845,497 requested in the Budget Transfer.
On January 31, 2017, the Board approved the transfer of $1 million from the General Fund to the Roads Fund for various 2017 Storm Projects to get the urgent work started. On February 26, 2019, the Board approved a transfer of $156,000 from the balance in the Roads Fund to the four projects. On June 4, 2019, the Board approved a transfer of $444,400 from the Measure T Fund to the four projects.
The Budget Transfer is to advance the County Measure T funds to start the construction. FEMA has obligated $2,624,142 funding for these projects to date. The match for these projects are 75% FEMA, 18.75% California Office of Emergency Services (Cal OES), and 6.25% local. After the Project has been completed, the County will submit actual project costs to FEMA and Cal OES. The reimbursements received from FEMA and Cal OES will be returned to Measure T funds.
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- FEMA has obligated funds and granted time extensions to December 2020 to complete the four projects. If the projects are not completed (or new extensions are not granted), the County will forfeit approximately $2,624,142 of FEMA funding and County will have to repair the slides with local funds.
- Is the General Fund Affected
- No
- Future Fiscal Impact?
- These projects are expected to be complete by December 2020. The future fiscal impact will be limited to routine maintenance of the roads.
- Consequences if not approved
- If not approved, the slides will continue and there will be additional damage to county roads and potential hazards to the public. FEMA has obligated funds and granted time extensions to December 2020 to complete the four projects and if not completed, the County will forfeit approximately $2,624,142 of FEMA funding.
- County Strategic Plan Pillar Addressed
- Livable Economy for All: Improve and maintain the existing transportation and road systems to safely accommodate all users.<BR>
- Additional Information
- On December 17, 2019, the Board approved the Five-year Measure T Project List, which includes $4,062,000 in Fiscal Year 2020-21 for the four projects. As of January 14, 2020, Measure T Non-Operating Special Revenue Fund has an available fund balance of $3,117,885, which is $727,612 short of the requested budget adjustment. However, the next quarterly disbursement of the funds is schedule to occur on January 20, 2020, and the amount is going to be $2,087,753 at which time sufficient funds will be available to transfer to the four projects.