Submitter

Director
Robert Peterson - Director - Public Works
Report By
Martha Burdick - Public Works Admin Manager - 259-8188
Agenda Date
Resolution / Ordinance
N
Category
SET MATTERS OR PUBLIC HEARINGS
Sub-Category
Subject
11:15 A.M. Adoption of resolution for implementation of energy retrofit projects
Special Instruction

RESOLUTION WILL NEED TO BE SIGNED BY BOARD CHAIR IMMEDIATELY IN ORDER TO SUBMIT TO THE CALIFORNIA ENEGY COMMISSION TIMELY.

Recommendation

Director of Public Works to provide presentation on Energy Management Plan projects and implementation and request adoption of a resolution authorizing the Chair to execute related loan agreement documents with the California Energy Commission (CEC).

Summary

Today's presentation will recap the previous Board decision to pursue energy saving projects for the Administration Building and Hall of Justice; update the Board on the improvements to be made, update the project costs for the proposed improvements, and recap the cost savings and payback as a result of implementing those improvements as briefly outlined in the Fiscal Impact section of this item.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?

California Energy Commission Loan

Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification

It is anticipated that in the first year of project completion the County will realize a net savings of approximately $153,000 of which $130,000 is a one time rebate from the CEC.  The anticipated net annual savings varies throughout the life of the loan (12 1/2 years), increasing from a low of $24,000 in year 2 to $41,450 and $128,350 in years 12 and 13.  

Is the General Fund Affected
No
Future Fiscal Impact?

It is anticipated that Property Management utility appropriations will be reduced following completion of these retrofit projects.

Consequences if not approved

The retrofit projects will not go forward

Additional Information
None

Impact

There is no Environmental Impact for this item.

Background

On June 3, 2003 Napa County retained Kenwood Energy to provide specialized consulting services on the development and implementation of an Energy Management Program for the Administration Building and Hall of Justice.  Tim Holmes of Kenwood Energy gave a PowerPoint presentation outlining potential energy savings projects, anticipated savings associated with each of those projects and the various funding mechanisms available to the County; the potential projects were electrical and mechanical in nature, with an anticipated rate of return of 20% or greater.  The Board directed staff to proceed with the Energy Management Plan process.

During the ensuing months, Public Works worked with the Consultant to develop a more refined list of projects that would have the greatest "bang for the buck" as well as meeting the criteria established by the California Energy Commission (CEC) for loan and rebate qualification.   Public Works solicited Requests for Proposals for both the lighing and mechanical system design.  Lighting Wizard was selected to perform a lighting audit and to design the lighting retrofit and Engineering Services, Inc.(ESI) was selected to evaluate and design one or two co-generation units, a water economiser cooling system, energy efficient motors and various Variable Frequency Drive fans and motors and other mechanical upgrades all aimed at reducing the costs for operating the Administration Building and Hall of Justice.

Public Works anticipates it will enter into agreements with each of the two vendors to further develop the designs for the proposed retrofit improvements.  Each of these agreements will require County Executive Office approval as specified under the recent legislation which raised the ceiling for requiring Board approval from $10,000 to $50,000.  When all the design work is complete, Public Works will return to the Board for approval of the plans and specifications and authorization to advertise for bid.

As required by the CEC, Public Works and the Consultant prepared a non binding Loan Application Budget for submission to the Commission in January 2004 in the amount of $822,578.  This budget included all costs associated with implementing the energy improvements for the Administration Building and Hall of Justice, and on April 23, 2004 the Commission notified Public Works that it had approved the budget application in the amount of $800,000 at 3.95% interest.  Included with their notification to the County were the Energy Conservation Assistance Account Loan Agreement and authorizing Resolution before you today for approval.

Todays presentation by Public Works and Tim Holmes of Kenwood Energy will update the Board on the recommended retrofit projects, update the project costs and review the cost savings as a result of implementing those improvements.