Steven Lederer - Director of Public Works - Public Works
Report By
Liang Chin Su - Junior Engineer - 7072598376
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
650 Imperial Way HVAC Upgrade Project, PW 18-03 - Approve Plans and Specifications
Recommendation
Director of Public Works requests the following:
Approval of and authorization for the Chair to sign Amendment No. 1 to Agreement No. 200264B with MK2 Engineers increasing maximum compensation by $2,480 for bidding support services for 650 Imperial Way HVAC Upgrade, PW 18-03 for a new not to exceed maximum of $48,595.
Approval of plans and specifications for the 650 Imperial Way HVAC Upgrade Project, PW 18-03 and authorization to advertise for sealed bids and opening of the bids at a time, date, and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code.
Pursuant to Public Contract Code Section 3400(c)(2), designate certain products (sole source Heating, Ventilation, and Air Conditioning controls) by Siemens in the plans and specifications for the construction of the project.
Summary
Air Conditioning Unit number 3 (AC3) which services a portion of a County owned building located at 650 Imperial Way is in need of an upgrade to a larger unit to meet the cooling demand of the building. The existing AC3 has required extensive maintenance and has consistently been unable to provide cooling relief to the tenants of the building due to being undersized.The new unit will meet current energy standards as well as provide dependable service for a portion of the facility which is occupied by Information Technology Services (ITS) staff.
On February 21st, 2020, the County Executive Officer signed an On-Call Mechanical Engineering Design Service Agreement for a maximum amount of $46,115 with MK2 Engineers for design and project services. Design has been completed and staff seeks authorization to put the project out to bid in order to move into the construction phase of the project. The Director of Public Works also requests approval of and authorization for the Chair to sign amendment number 1 with MK2 Engineers increasing the maximum compensation by $2,480, for a new maximum of $48,595 for bidding and construction support.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Approval of the plans and specifications and authorization to advertise for bids is necessary to move the project forward toward construction.
Is the General Fund Affected
Yes
Future Fiscal Impact?
Construction is expected to commence in Fiscal Year 2020-21 and be complete in 2020-21. The future fiscal impact will be limited to routine maintenance of the air conditioning unit from Property Management.
Consequences if not approved
The project will not proceed to the construction phase, the office will not receive sufficient cooling and the staff of the building will feel the discomfort during hot summer days.
County Strategic Plan Pillar Addressed
Healthy, Safe, and Welcoming Place to Live, Work, and Visit - Provide comfort to the staff in the Information Technology Service office during hot summer days.<BR>
Impact
Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.
Background
The heating, ventilation, and air conditioning (HVAC) system at 650 Imperial Way was installed in 2006. Property Management has received many complaints from the current tenants, Information Technology Service (ITS), that the facility is uncomfortably hot in the summer, and the staff felt no cooling in the office space. In July 2016, program 17007 was created and a budget of $59,000 was allocated to upgrade the controls system of the AC unit. Over the years and through various site visits, engeering analysis, and prior plans review, County staff has determined that the unit needs to be replaced with a larger unit along with a controls upgrade in order to provide sufficient cooling to the office space.
In February 2020, the County CEO signed a Professional Service Agreement (PSA) in the amount of $46,115 with MK2 Engineers to provide on-call mechanical engineering design services to upgrade the HVAC system at 650 Imperial Way. MK2 and the Public Works staff have since conducted multiple site visits and unit inspection and determined the most cost efficient method to upgrade the existing HVAC system to provide comfort to the staff in the ITS office.
Today, the Director of Public Works is proposing approval of Amendment No. 1 to MK2 Engineers PSA for a new total not to exceed amount of $48,595. The proposed amendment increases the 650 Imperial Way HVAC design amount by $2,480 to include bidding support services. This proposal does not require a budget transfer as the additional amount will be offset by the revenue previously allocated to Public Works engineering and administrative time.
The current engineer's project estimate is approximately $737,361, but that cost will be revised based on actual bids. Staff will return to the Board at time of construction award and to request a budget transfer to fully fund the Project based on actual bids, with the funds coming from the Accumulated Outlay Fund. The Director of Public Works recommends that the Board approve the plans and specifications for bidding.
Since 2003, Siemens Industry, Inc. (formerly Siemens Building Technologies, Inc.) has provided specialized services relating to technical support for the HVAC control equipment located in multiple County owned facilities. The Director of Public Works is proposing an upgrade to the existing control system along with the new AC unit replacement to assist Property Management with future maintenance at 650 Imperial Way. The existing system in the building utilizes Siemens control system which are being sole sourced for this project to assure future communications compatibility and because they have proven to be reliable at the facility. Utilizing Siemens products provides the additional benefit of limiting the upgrade of the control system to the rooftop units instead of the entire building which keeps cost to minimum. The current engineer's estimate for the controls upgrade is $90,000 which is included in the construction estimate above.