Subject
650 Imperial Way HVAC Upgrade Project, PW 18-03 - Award of Construction Contract; Amendment to Professional Services Agreement No. 200264C with MK2 Engineers

Recommendation

Director of Public Works requests the following:

  1. Award of the contract for the "650 Imperial Way HVAC Upgrade Project, PW 18-03" to the lowest bidder, Trahan Mechanical Inc. of San Rafael, California, for their base bid of $384,200, and approve the additive alternate for a cost of $197,200 for a total construction contract of $581,400 and authorize the Chair to sign the construction contract;  
  2. Approval of and authorization for the Chair to sign Amendment No. 2 to Agreement No. 200264C with MK2 Engineers increasing maximum compensation by $18,400 for 650 Imperial Way HVAC Upgrade Project, PW 18-03 for a new maximum of $66,995 for additional construction support services; and
  3. Approval of Budget Transfer No. DPW026 for the following (4/5 vote required):
    1. Increase appropriations by $814,303 in the Accumulated Capital Outlay Fund (ACO) (Fund 3000, Subdivision 3000000) with the use of its available fund balance to be transferred to Program 17007; and
    2. Increase appropriations by $814,303 in Program 17007 (650 Imperial Way HVAC Upgrade Project, PW 18-03) budget offset by an increase in revenue from the transfer from the ACO.

Summary

Air Conditioning Unit number 3 (AC3) which services a portion of a County owned building located at 650 Imperial Way is in need of an upgrade to a larger unit to meet the cooling demand of the building. The existing AC3 has required extensive maintenance and has consistently been unable to provide cooling relief to the tenants of the building due to being undersized. The new unit will meet current energy standards as well as provide dependable service for a portion of the facility which is currently occupied by Information Technology Services (ITS) staff. Public Works staff also recommends replacing the old existing heating units (3 units) which was included in the bid as an additive alternate.

On February 21, 2020, the County Executive Officer signed an On-Call Mechanical Engineering Design Service Agreement for a maximum amount of $46,115 with MK2 Engineers for design and project services. On September 13, 2020, the Board of Supervisors approved the 650 Imperial Way HVAC Upgrade Project Plans and Specifications and authorization to advertise for sealed bids and opening of the bids pursuant to Section 20150.8 of the Public Contract Code. As indicated in the September 13, 2020, agenda item, a budget transfer is being requested to award the construction contract, amend the existing professional service agreement with MK2 for additional construction support, and will fully fund the project.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
Approval of the construction contract award is necessary for project to move to construction resulting in improved energy efficiency and lower maintenance costs.
Is the General Fund Affected
Yes
Future Fiscal Impact?
Construction is expected to commence in Fiscal Year 2020-21 and be complete in 2020-21.  The future fiscal impact will be limited to routine maintenance of the air conditioning unit from Property Management.
Consequences if not approved
The project will not proceed to the construction phase, the building will not receive sufficient cooling resulting in higher cost maintenance costs related to Property Management staff time and replacement parts.
County Strategic Plan Pillar Addressed
Healthy, Safe, and Welcoming Place to Live, Work, and Visit - Provide comfort to the staff in the Information Technology Service office during hot summer days.<BR>

Impact

Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.

Background

The heating, ventilation, and air conditioning (HVAC) system at 650 Imperial Way was installed in 2006. Property Management has received many complaints from the current tenants, Information Technology Service (ITS), that the facility is uncomfortably hot in the summer, and the staff felt no cooling in the office space. In July 2016, program 17007 was created and a budget of $59,000 was allocated to upgrade the controls system of the AC unit. Over the years and through various site visits, engeering analysis, and prior plans review, County staff has determined that the existing HVAC unit needs to be replaced with a larger unit along with upgraded control system in order to provide sufficient cooling to the office space.

In February 2020, the County CEO signed a Professional Service Agreement (PSA) in the amount of $46,115 with MK2 Engineers to provide on-call mechanical engineering design services to upgrade the HVAC system at 650 Imperial Way. MK2 and the Public Works staff have since conducted multiple site visits and unit inspection and determined the most cost efficient method to upgrade the existing HVAC system to provide comfort to the staff in the ITS office.

On September 15, 2020, the Board of Supervisors approved plans and specifications for this Project and authorized the Director of Public Works to advertise and open bids for the project pursuant to Section 20150.8 of the Public Contract Code. Below are the bid results from the October 29, 2020 Bid Opening:

Bidders                                                              Base Bid Additive
Alternate
SH Mechanical Inc. of Suisun City, CA $ 290,199 $ 103,457
Trahan Mechanical Inc. of San Rafael, CA $ 384,200 $ 197,200
S&H Construction Inc. of Fremont, CA $ 393,000 $ 206,000
Dowdle & Sons Mechanical of American Canyon, CA $ 399,700 $ 80,700
Bell Products Inc. of Napa, CA $ 419,732 $ 148,950
Emcor Mesa Energy Systems of Sacramento, CA $ 428,616 $ 151,457
GECO Inc. of Novato, CA $ 774,000 $ 286,700

While SH Mechanical Inc. was the original apparent lowest bidder, SH Mechanical Inc. submitted a 'claims of mistake' in accordance with Public Contract Code Section 5100 and notified the County of a subcontractor not listed on their bid package which led to their bid being lower than their intended price. As a result, the bid from SH Mechanical Inc. is considered incomplete and SH Mechanical Inc has formally withdrawn their bid. Therefore, Trahan Mechanical Inc. of San Rafael, CA is the lowest bidder.  The low bid of $384,200 is less than the engineer's construction cost estimate of $515,000. The Director of Public Works recommends the Board of Supervisors approve the additive alternate work for cost of $197,200 as the total project cost is of good value to the County to replace old existing heating units that are beyond their useful lives and need replacement. The total construction contract will be $581,400.  The total project budget with the addition of engineering design, construction management, project management, special inspection and contingency is $873,303. In addition to a previous appropriation of $59,000, a budget transfer of $814,303 is needed to move this project to construction.

Trahan Mechanical Inc. is not a local vendor however, the Public Contract Code requires that the construction contract be awarded to the lowest responsible bidder regardless of whether the low bidder is local or not. Staff reached out to the local construction contractor community by advertising the request for bids in the Napa Valley Register and the Solano-Napa Builder's Exchange, and by posting on the County website. Staff also sent "Notices to Contractors" to the local construction community. Once the construction contract is awarded the County will contact the Napa County Workforce Investment Board (WIB) and require the successful contractor to contact the WIB and let the WIB know of its hiring needs.

The Director of Public Works recommends approval of the requested budget transfer and award of the contract for the 650 Imperial Way HVAC Upgrade Project, PW 18-03, to Trahan Mechanical Inc. of San Rafael, California, for their low base bid of $384,200.

The Director of Public Works also recommends approval of and authorization for the Chair to sign an Amendment No. 2 with MK2 Engineers increasing the maximum compensation by $18,400 for 650 Imperial Way HVAC Upgrade Project, PW 18-03 (Program 17007) for a new maximum of $66,995 for MK2 Engineers to provide structural detail drawings for the support on the AC units as well as provide support to the County staff during construction meetings and review as-built drawings.