- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- Yes
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
The proposed project will stabilize the roadway near Mt. Veeder MPM 5.1 and reconstruct the two-lane road. The requested approvals will allow for the solicitation for construction bids and move the project forward toward construction.
- Is the General Fund Affected
- No
- Future Fiscal Impact?
- Remaining budget from Fiscal Year 2020-2021 will be carried over to the Fiscal Year 2021-2022 budget.
- Consequences if not approved
If not approved, the road will remain one lane and the site could continue to fail in the event of further heavy rains.
- County Strategic Plan Pillar Addressed
- Livable Economy for All - improve and maintain the existing transportation and roads system to safely accommodate all users.
- Additional Information
- To date roughly $68,895 has been paid out for design out of the $152,300 budgeted. Additional funds will be needed for construction support and special testing at time of award.