Submitter

Director
Steven Lederer - Director of Public Works - Public Works
Report By
Dewey Phan - Assistant Engineer -
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
2014 Earthquake Repair - Third Ave Culvert and Bridge, RDS 17-32 and RDS 17-33 - Award of Construction Contract

Recommendation

Director of Public Works requests the following actions for two Roads Capital Improvement Projects necessary due to damage sustained during the 2014 Earthquake: 

  1. Approval of Budget Transfer No.DPW 047 for the following (4/5 vote required):   
    1. Increase appropriation by $629,048 in the Accumulated Capital Outlay (ACO) Fund budget (Fund 3000, Sub-Division 3000000) offset by the use of its available fund balance to fund the following:
    2. Increase appropriation by $26,239 in Third Ave mile post marker (MPM) 0.06, RDS 17-32, project budget in the Roads CIP budget (Fund 2040, Sub-Division 2040500, Program R8120) offset by increase in revenue from the transfer from the ACO; and 
    3. Increase appropriation by $602,809 in Third Ave MPM 1.75, RDS 17-33, project budget in the Roads CIP budget (Fund 2040, Sub-Division 2040500, Program R8130) offset by increase in revenue from the transfer from the ACO; and
  2. Award of the construction contract for the "Third Ave. Culvert (LOP 208) MPM 0.60, RDS 17-32 and Third Ave. Bridge (LOP 209) MPM 1.75, RDS 17-33," to Granite Rock Company of San Jose, California, for their low base bid of $369,208 and authorization for the Chairman to sign the construction contract.

Summary

During the 2014 earthquake, the subject sites sustained significant damages as follow:

  • Third Ave MPM 0.06, RDS 19-32 - Structure cracks at the historic stone culvert headwall.
  • Third Ave MPM 1.75, RDS 19-33 - Structure cracks at the bridge concrete headwall.

For the Third Ave Culvert, the proposed repair is to seal the cracks at the historic stone culvert headwall with mortar.  For the Third Ave Bridge, the proposed repair is to replace the damaged concrete headwall and construct a new concrete retaining wall supported on 18-inch cast-in-drilled-hole (CIDH) piles.

The successful bidder is Granite Rock Company for their low total base bid of $369,208.  Construction is anticipated to commence in June 2021 and to be completed by October of 2021, weather permitting. Although the Board approved some initial funding a budget transfer is needed to be able to complete this FEMA funded project. After project completion funding amounts are expected to be adjusted by FEMA for actual project costs. 

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
Funding is coming from the Accumulated Capital Outlay Fund in advance of reimbursement from FEMA and Cal OES. The project was partially budgeted for design and additional budget is requested for construction. Budget for the project are included in Roads CIP budget, Fund 2040 Subdivision 2040500 Program R8120 and Program R8130.  On 2/12/21, FEMA obligated $544,867 funding for these projects as part of PW 155.  The match for these projects is 75% FEMA, 18.75% California Office of Emergency Services (Cal OES) and 6.25% local. After the projects have been completed, the County will submit actual project costs to FEMA and Cal OES for consideration.  The reimbursements received from FEMA and Cal OES will be returned to ACO funds.

Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
FEMA has obligated funds and granted time extensions to December 2021 to complete the two projects.  If the projects are not completed (or new extensions are not granted), the County will forfeit approximately $544,867 of FEMA funding.
Is the General Fund Affected
Yes
Future Fiscal Impact?

Construction is anticipated to commence this summer 2021 and be completed in the next fiscal year 2021-2022.  The future fiscal impact should be limited to routine maintenance of the road, culvert, and bridge however permitting agencies may require future planting maintenance.


Consequences if not approved
If not approved, repairs to Third Ave Culvert (LOP 208) and Bridge (LOP 209) cannot be completed, the structures and overlaying roadways will continue to deteriorate, and the bridge and historic culvert could fail during another earthquake or severe storm. Additionally, the County will have to return all federal funds received to date for the engineering phase.
County Strategic Plan Pillar Addressed
Healthy, Safe, and Welcoming Place to Live, Work, and Visit<BR>
Additional Information
On December 5, 2017, the Board approved a budget transfer (DPW035) to fund $30,000 initial design costs for Third Ave Project (Program R8120, 2040500) and $130,000 for Third Ave Project (Program R8130, 2040500).  

This budget adjustment was not included as part of the mid-year budget estimates as budget adjustments for Capital Improvement Projects are adjusted as contracts are awarded in order to create a budget that is most accurate.

Impact

Consideration and possible adoption of a Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.] FEMA has determined that the project qualifies for a categorical exclusion under the National Environmental Policy Act.

Background

During the 2014 earthquake, the subject sites sustained significant damages as described above.  The proposed repair for each site is as follows:

Third Ave Culvert (LOP 208) MPM 0.60, RDS 19-32:
The proposed repair is to seal the cracks at the historic stone culvert with mortar.

Third Ave Bridge (LOP 209) MPM 1.75, RDS 19-33:
The proposed repair is to replace the damaged headwall and construct a new retaining wall supported on 18-inch cast-in-drilled-hole (CIDH) piles.  The existing bridge barrier and guardrail will also be removed and replace with a new concrete barrier and guardrail, respectively.

On March 27, 2019, the Board approved a rejection to the first bid due to an unfavorable bid result at the time and authorized staff to re-bid the projects.  The projects were re-advertised for bidding on February 4, 2020.  Bids were open on February 27, 2020, and four bids were received.

Granite Rock Co.              San Jose, CA $369,208.00
J.A. Gonsalves & Son Napa, CA $413,758.00
Team Ghilotti Petaluma, CA $462,881.10
Swierstok Enterprises Orangevale, CA $568,000.00

The successful bidder is Granite Rock Co. for their low total base bid of $369,208.  The engineer's estimate was $345,300.  Construction is anticipated to commence in June 2021 and to be completed by October of 2021, weather permitting.  The estimated total project budget for the two sites is $793,049 which includes engineering design, project administration, construction, and construction management as shown in the attached spreadsheets. The construction cost for the two project sites is $369,208 and 25% construction contingency of $92,302 is being requested.

The above projects qualified for federal funding and the Federal Emergency Management Agency (FEMA) has obligated funds and granted time extension to December 2021 for these projects.  For FEMA funded projects, the match is 75% FEMA, 18.75% California Office of Emergency Services (Cal OES), and 6.25% local (Roads funds). FEMA has authorized $544,867 for the repair of these projects and at project completion is expected to pay for actual costs.

To date, the Board has appropriated a total of $164,000 for the two projects and an additional appropriation in the amount of $629,048 is requested to repair the structural damages at the culvert and bridge on Third Ave.

It is recommended that the Board award the contract to Granite Rock Co. for their low bid of $369,208, approve the budget transfer, and authorize the Chair to sign the construction contract.