- Is there a Fiscal Impact?
- Yes
- Is it Currently Budgeted?
- No
- What is the revenue source?
- Funding is coming from the Accumulated Capital Outlay Fund in advance of reimbursement from FEMA and Cal OES. The project was partially budgeted for design and additional budget is requested for construction. Budget for the project are included in Roads CIP budget, Fund 2040 Subdivision 2040500 Program R8120 and Program R8130. On 2/12/21, FEMA obligated $544,867 funding for these projects as part of PW 155. The match for these projects is 75% FEMA, 18.75% California Office of Emergency Services (Cal OES) and 6.25% local. After the projects have been completed, the County will submit actual project costs to FEMA and Cal OES for consideration. The reimbursements received from FEMA and Cal OES will be returned to ACO funds.
- Is the activity Mandatory or Discretionary
- Discretionary
- Discretionary Justification
- FEMA has obligated funds and granted time extensions to December 2021 to complete the two projects. If the projects are not completed (or new extensions are not granted), the County will forfeit approximately $544,867 of FEMA funding.
- Is the General Fund Affected
- Yes
- Future Fiscal Impact?
-
Construction is anticipated to commence this summer 2021 and be completed in the next fiscal year 2021-2022. The future fiscal impact should be limited to routine maintenance of the road, culvert, and bridge however permitting agencies may require future planting maintenance.
- Consequences if not approved
- If not approved, repairs to Third Ave Culvert (LOP 208) and Bridge (LOP 209) cannot be completed, the structures and overlaying roadways will continue to deteriorate, and the bridge and historic culvert could fail during another earthquake or severe storm. Additionally, the County will have to return all federal funds received to date for the engineering phase.
- County Strategic Plan Pillar Addressed
- Healthy, Safe, and Welcoming Place to Live, Work, and Visit<BR>
- Additional Information
- On December 5, 2017, the Board approved a budget transfer (DPW035) to fund $30,000 initial design costs for Third Ave Project (Program R8120, 2040500) and $130,000 for Third Ave Project (Program R8130, 2040500).
This budget adjustment was not included as part of the mid-year budget estimates as budget adjustments for Capital Improvement Projects are adjusted as contracts are awarded in order to create a budget that is most accurate.