Submitter

Director
Steven Lederer - Director of Public Works - Public Works
Report By
Dewey Phan - Assistant Engineer -
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
2017 Storm Slide Repair, Mt. Veeder Road MPM 5.1, RDS 19-13, Construction Contract Award

Recommendation

Director of Public Works requests the following:

  1. Award of the construction contract for the "2017 Storm Slide Repair, Mt. Veeder Road MPM 5.1, RDS 19-13" to Piazza Construction of Petaluma, California, for their low base bid of $1,053,604.05 and authorization for the Chair to sign the construction contract; and 
  2. Approval Budget Transfer No. DPW050 for the following (4/5 vote required):
    1. Increase appropriations by $1,472,346 in the Measure T Non-Operating Special Revenue Fund to transfer to Program S7304 offset by use of its available fund balance; and
    2. Increase appropriations by $1,472,346 in Program S7304 (Mt. Veeder Road MPM 5.1, RDS 19-13) budget offset by an increase in revenue from the transfer from the Measure T SRF budget.

Summary

During heavy rains in 2017, the embankment supporting roughly 400 feet of roadway near mile post marker (MPM) 5.1 of Mt. Veeder Road slid downslope. The roadway has since been reduced to a single lane while design and environmental work for a concrete grade beam retaining wall took place. On March 18,2021 bids were received for the design which will restore the integrity of the site before winter if construction is approved. To date the Board has approved enough funding to design and bid this project with the understanding that once bids were opened a budget transfer would be requested based on the bid results to fund the remainder of the project.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
No
What is the revenue source?
Funding is coming from the Measure T Special Revenue Fund.  On February 26, 2019 the Board approved Budget Transfer No. DPW025 and on June 4, 2019 the Board approved Budget Transfer No. DPW044 which increased appropriations by $18,000 and $134,300 respectively in the Roads Department Capital Improvement Program (CIP) Budget- Fund 2040, Subdivision 2040500, Program S7304 for this Mt. Veeder Road MPM 5.1 project. These initial budget transfers provided Measure T funds to cover the design and bidding phases of the project which are now complete and another budget transfer is needed for the construction phase.

Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification

The proposed project will stabilize the roadway near Mt. Veeder MPM 5.1 and repair damage that occurred during the 2017 storms that has reduced the roadway to a single lane. The requested approvals will allow for the construction of the repair.  

Is the General Fund Affected
No
Future Fiscal Impact?
Remaining budget from Fiscal Year 2020-2021 will be carried over to the Fiscal Year 2021-2022 budget.
Consequences if not approved

If not approved, the site could continue to fail in the event of further heavy rains.



County Strategic Plan Pillar Addressed
Livable Economy for All - improve and maintain the existing transportation and roads system to safely accommodate all users.
Additional Information
To date roughly $69,558 has been paid out for design and project management out of $152,300 budgeted.

Impact

Consideration and possible adoption of a Categorical Exemption Class 1:It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]

Background

During heavy rains in 2017 the embankment supporting roughly 400 feet of roadway near MPM 5.1 of Mt. Veeder Road slid downslope and reduced the roadway to a single lane. On January 31, 2017 the Board approved $1,000,000 to start the design process on a series of damaged sites including Mt. Veeder Road MPM 5.1. A design was developed for the construction of a concrete grade beam retaining wall that will restore the integrity of the site and allow both lanes to be open. The Board authorized advertising for the project on February 23, 2021 and County staff opened 11 bids on March 18, 2021 with the following results:

Piazza Construction Petaluma, CA $1,053,605.05          
Maggiora & Ghilotti San Rafael, CA  $1,057,057.00 
Granite Construction Co. Ukiah, CA  $1,082,405.87 
Gordon N. Ball, Inc. Alamo, CA  $1,083,727.50 
Pat Nelson Construction, Inc. Petaluma, CA  $1,100,254.05 
Bridgeway Civil Constructors, Inc.      Vacaville, CA  $1,106,226.30 
Suulutaaq, Inc. Suisun City, CA  $1,106,369.00 
Azul Works, Inc. San Francisco, CA  $1,142,922.00 
Ghilotti Construction Co. Santa Rosa, CA  $1,161,982.75 
Thompson Builders Co. Novato, CA   $1,241,614.00 
Marshall Brothers Enterprises, Inc. Livermore, CA $1,353,620.75


The lowest responsive base bid of $1,053,605.05 from Piazza Construction of Petaluma, California is under the engineer's construction cost estimate of $1,250,000. The total project budget with the addition of engineering design, construction management, project management, special inspection and contingency is $1,624,646 and will be funded with Measure T funds (see attached project budget). In addition to a previous appropriations of $152,300, a budget transfer of $1,472,346 is needed to move this project forward. 

Piazza Construction is not a local vendor however, the Public Contract Code requires that the construction contract be awarded to the lowest responsible bidder regardless of whether the low bidder is local or not. Staff reached out to the local construction contractor community by advertising the request for bids in the Napa Valley Register and the Solano-Napa Builder's Exchange, and by posting on the County website. Staff also sent "Notices to Contractors" to the local construction community. Once the construction contract is awarded the County will contact the Napa County Workforce Investment Board (WIB) and require the successful contractor to contact the WIB and let the WIB know of its hiring needs.

Director of Public Works requests approval of the requested budget transfer and award of the contract for the "2017 Storm Slide Repair, Mt. Veeder Road MPM 5.1, RDS 19-13" to Piazza Construction of Petaluma, California, for their low base bid of $1,053,605.05, and authorization for the Chair to sign the construction contract.