Juan Arias - PRINCIPAL PUB WORKS ENGINEER - 259-8374
Agenda Date
Resolution / Ordinance
N
Category
ADMINISTRATIVE ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
2005/2006 Flood - Remaining Permanent Repair Projects - Status Update
Recommendation
Director of Public Works to present an update on the status of the remaining permanent repair projects related to the 2005/2006 flood events and to request approval of plans and specifications, authorization to advertise for sealed bids and opening of the bids at a time, date and location to be published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code for the following projects:
Diamond Mountain Road Project, RDS 07-29
4700 Block Redwood Road Project, RDS 07-03
Steele Canyon MPM 2.00 Road Project, RDS 07-26
Steele Canyon MPM 2.25 Road Project, RDS 07-27
Summary
At the February 5, 2008 Board meeting the Director of Public Works presented a status report on remaining projects related to the 2005/2006 flood events and on the the Federal Emergency Management Agency (FEMA)/Office of Emergency Services (OES) funding commitments. An update was provided at that time because it was uncertain if FEMA would respond in a timely manner to the scope change, or whether it would agree to provide a funding commitment for the requested scope changes. This had potential financial ramifications to the County given that the projects are presently required by FEMA to be completed in 2008. Based upon the FEMA response, Public Works was to return to the Board no later than May with further analysis and recommendations on how to proceed.
OES/FEMA have approved the scope change requests for four of the five projects and environmental clearances for the scope changes on three of the projects. Staff anticipates environmental clearance on the remaining project and needs to bid the projects so as to construct them during this summer/fall. After bid opening, staff will return to the Board with requests to award construction contracts for projects that receive all environmental approvals.
FEMA has denied the scope change request for the remaining fifth project (Spring Mountain Road, RDS 07-17). However, FEMA did determine that it needed to revise its original scope in a different manner than proposed by the County. The Department concurs that the proposed revised scope by FEMA does address the geo-technical issues that prompted the Department to request its original scope change. This will result in additional funding for this project, and the need the Department to expedite the design process for this revised scope in order to construct this improvement by this summer/fall. The Department will make every effort to return to the Board in June with a request to approve plans and specifications and authorization to advertise for sealed bids for the Spring Mountain project.
Procedural Requirements
Staff reports.
Public comments.
Motion, second, discussion and vote on the item.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification
These repairs are required because of the 2005/06 flood events and the County receives 100% reimbursement through FEMA/OES.
Is the General Fund Affected
Yes
Future Fiscal Impact?
Construction costs are expected to be incurred during fiscal year 2008/2009 for the four projects.
Consequences if not approved
Staff will not be able to move projects into construction this summer; therefore missing the FEMA completion deadlines and jeopardizing funding. Expenditure commitment will be sought at time of award of contract.
Additional Information
Technically, the General Fund is affected by all projects related to the Road Fund given the outstanding General Fund loan made for the declared emergency caused by the storms of December 2005 and April 2006.
Impact
ENVIRONMENTAL DETERMINATION: These projects are subject to the California Environmental Quality Act (CEQA) process and the National Environmental Policy Act (NEPA) process. The CEQA and NEPA determinations are as follows:
For CEQA determination, the determination is as follows for all 5 projects:
Categorical Exemption Class 1: It has been determined that this type of project does not have a significant effect on the environment and is exempt from the California Environmental Quality Act. [See Class 1 (“Existing Facilities”) which may be found in the guidelines for the implementation of the California Environmental Quality Act at 14 CCR §15301; see also Napa County’s Local Procedures for Implementing the California Environmental Quality Act, Appendix B.]
For NEPA determination, the determination is as follows:
Spring Mountain Road and Steele Canyon Road 2.0 were found to be Statutorily Excluded: It has been determined that this type of project which does not have a significant environmental effect and is excluded from the requirement to prepare an Environmental Assessment or Environmental Impact Statement. Spring Mountain is being reevaluated due to scope change but staff does not anticipate a change on NEPA determination.
Steele Canyon 2.25 was determined to be Categorically Excluded. A biologist verified that no Elderberry Longhorn Beetles were present at that time and required that any impacted Elderberry bushes be replaced at the conclusion of construction.
Redwood Road was determined to be Categorically Excluded. Section 7 consultation concluded that the area is potentially suitable habitat for the Central California Coast Steelhead. It is also potential habitat for bald eagle and northern spotted owl. Conservation measures imposed limit the working period to September 15 through October 15.
Diamond Mountain Road which was initially determined to be Statutorily Excluded, is now under environmental review. The site visit was made May 6, and staff awaits the determination. Diamond Mountain is being reevaluated due to scope change but staff does not anticipate a change on NEPA determination.
Background
At the February 5, 2008 meeting the Department informed the Board that it had submitted scope and estimated cost updates to OES/FEMA for environmental review, if necessary, and for funding consideration based on the geo-technical studies and engineering design of five eligible projects that had a completion deadline of the autumn of 2008. The projects are identified as: 1) Diamond Mount Road, 2) 4700 Block Redwood Road, 3) Spring Mountain Road, 4) Steele Canyon Mile Post Marker (MPM) 2.00, and 5) Steele Canyon Mile Post Marker (MPM) 2.25. Staff presented the following possible scenarios to the Board for these five projects:
Lack of Timely Response to Scope Change Request
Rejection of Scope Change Requests
Approval of Scope Change Requests
Since then, staff has received the following approvals on projects scheduled for construction this summer and fall:
4700 Block Redwood Road- Scope Change Approval and Environmental Clearance on Scope Change - $722,423 approved
Steele Canyon MPM 2.00 - Scope Change Approval and Environmental Clearance on Scope Change - $1,425,995 approved
Steele Canyon MPM 2.25 - Scope Change Approval and Environmental Clearance on Scope Change - $282,726 approved
It is necessary to move forward and authorize to advertise for sealed bids if the Department is to meet the FEMA requirement to complete these projects by autumn of 2008. Before returning to the Board for the authorization to award bids, the Department will continue to prompt FEMA to provide the environmental clearance on the Diamond Mountain Road project where the scope change has been authorized. If FEMA fails to provide this environmental clearance in a timely manner, there is an automatic extension of the construction deadline because the project cannot be constructed without this environmental clearance.
FEMA has denied the scope change request for the remaining fifth project (Spring Mountain Road, RDS 07-17). However, FEMA did determine that it needed to revise its original scope in a different manner than proposed by the County. This will result in additional funding for this project for a new total amount of $344,548. The Department will need to expedite the design process for this revised scope in order to construct this improvement by this summer/fall. The Department concurs that the proposed revised scope by FEMA does address the geo-technical issues that prompted the Department to request its original scope change. The Department will make every effort to return to the Board in June with a request to approve plans and specifications and authorization to advertise for sealed bids for the Spring Mountain project. While making every effort to expedite this project, the Department will also submit a request to FEMA/OES to extend the deadline of this project until 2009 to ensure the County does not lose the FEMA/OES revenue obligated for this project.
The following information provides a summary of the remaining issues to be resolved with FEMA pertaining to the 2006/06 flood events.
UNRESOLVED CLAIMS
The County has submitted approximately two hundred claims for disaster related damages. The County still has six claims not yet resolved with FEMA/OES. The six claims not yet resolved with FEMA are those for:
Projects completed under appeal
Ineligible projects under review
Eligible project under review for scope change authorization
Projects Completed Under Appeal
FEMA has rejected funding commitments for two projects, Circle Oaks and Redwood Road. They are now under appeal. The final fiscal outcome for funding these projects is dependent upon this appeal process. Potential outcomes include:
Best Case Scenario - 100% Funding through FEMA/OES ($1.7 million)
Middle Case Scenario - 75% Funding through OES ($1.3 million) and 25% Funding through County ($0.4 million)
Worst Case Scenario - 100% Funding through County ($1.7 million)
Ineligible Projects Under Review
3 locations, Dry Creek Road, Whitehall Road, and White Sulphur Springs Road, are still under FEMA review where $1.75 million in repair damages are estimated.
Eligible project under review for scope change authorization
4800 Block of Redwood Road (Sites 1 and 2) have been authorized for funding in the amount of $355,911. Based upon geo-technical studies and engineering design, the Department is in the process of requesting a scope change that will require funding in the amount of $1.7 million. This project is scheduled for completion in the autumn of 2009.
Attachment A provides a summary of the 2005/06 flood repair projects to be completed.