Submitter

Director
Robert Peterson - Director - Public Works
Report By
FRANK LUCIDO - ASSOCIATE MECHANICAL ENGINEER - 259-8377
Agenda Date
Resolution / Ordinance
N
Category
ADMINISTRATIVE ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
2005/2006 Flood - Remaining Permanent Repair Projects - Authorization to Award Construction Contract

Recommendation

Director of Public Works requests the following actions regarding "Spring Mountain Road Viaduct", FEMA PW 3538, RDS 07-17:                                          

  1. Present the results of bid solicitation; 
  2. Provide recommendation for the award of the contract; and 
  3. Authorization for the Chair to sign the construction contracts consistent with the award recommendations.

Summary

On June 17, 2008 the Board authorized the Director of Public Works to open bids for the "Spring Mountain Road Viaduct", FEMA PW 3538, RDS 07-17 at a time, date and location published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code.   As a result of the bid openings, the Director of Public Works is recommending award to the successful bidders and authorization for the Chair to sign the construction contracts for this project.

This action is being expedited without knowing the results of the competitive bidding process at the time of the preparation of this agenda item given the limited timeframe that the Federal Emergency Management Agency (FEMA) has provided for the completion of these projects by October 14, 2008.
 
Procedural Requirements

  1. Staff reports 
  2. Public comments.
  3. Motion, second, discussion and vote on the item.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification

These repairs are required because of the 2005/06 flood events and the County receives 100% reimbursement through FEMA/Office of Emergency Services (OES).    

Is the General Fund Affected
No
Future Fiscal Impact?

None

Consequences if not approved

Staff will not be able to move projects into construction this summer; therefore missing the FEMA completion deadlines and jeopardizing funding. 

Additional Information

While this project is fully funded through FEMA/OES revenue, there still is uncertainty regarding $1.7 million in FEMA/OES reimbursement pertaining to the completed repairs for Redwood Road and Circle Oaks that are presently in a second round of appeals.  The Department has recently received a FEMA denial letter on the second appeal regarding Redwood Road, and is in the process of reviewing other options to recover at least part of our costs.  The Department will address this issue as part of a future agenda item that will provide Surface Treatment Project recommendations for the $1.9 million of additional General Fund contribution added to the Roads budget as part of the approved FY 2008-09 budget.

Impact

ENVIRONMENTAL DETERMINATION: The proposed actions are not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

Background

On June 17, 2008 the Board of Supervisors approved plans and specifications for the "Spring Mountain Road Flood Repair Project" and authorized the Director of Public Works to open bids at a time, date and location published by the Director of Public Works pursuant to Section 20150.8 of the Public Contract Code. 

The repair at Spring Mountain Road consists of a half bridge structure constructed on drilled piers.  The County has met with representatives from the Spring Mountain Association (SMDA) to coordinate the best times for closure and included its recommendations into the construction contract.  Staff will involve SMDA during the bidding and preconstruction process to ensure that its concerns are dealt with prior to beginning of construction.  Staff will be in constant communication with SMDA during construction to ensure that residents and businesses in the area are minimally impacted.   

Bids were solicited and opened July 17.  Staff is presenting the result of that bidding process today and requesting the Board award the construction contract to the successful low bidder and authorize the Chair to execute the construction contract. 

Attachments

There are no attachments to this item