Submitter

Director
Robert Peterson - Director - Public Works
Report By
Todd Adams - Stormwater Program Specialist - 253-4823
Agenda Date
Resolution / Ordinance
N
Category
CONSENT ITEMS
Sub-Category
Community Resources & Infrastructure
Subject
Amendment No. 4 to Agreement No. 6054 to Increase Funding for the County-wide Stormwater Program
Agreement
6054
Special Instruction

9 original signed copies are needed. Please send them to Greg at the Flood District when they are signed.

Recommendation

Director of Public Works requests approval of and authorization for the Chair to sign Amendment No. 4 to Agreement No. 6054 with the Napa County Flood Control and Water Conservation District increasing the County's cost by $5,933 for a new maximum of $34,408 extending the term through June 30, 2009 for development and implementation of an updated Napa County Stormwater Management Program.

Summary

There is the need to increase the proportional cost reimbursement obligations set forth in Agreement 6054 by $20,000 to fund additional staff time to coordinate the development of a new Stormwater Management Program and to increase education and outreach efforts.  All other terms and conditions of the agreement will remain unchanged. 

These costs are shared by formula between the cities of Napa, St. Helena, Calistoga, American Canyon, the Town of Yountville and the County.  Approval of Amendment No. 4 of Agreement No. 6054 will increase the County's contribution from $28,475 to $34,408.

Fiscal Impact

Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Discretionary
Discretionary Justification

Contracting with the Flood District is the most economical and efficient way to provide for these services which are mandated through the National Pollutant Discharge Elimination System program.

Is the General Fund Affected
Yes
Future Fiscal Impact?

None.

Consequences if not approved

The violation of any permit condition of the Phase II Municipal Stormwater General Permit is punishable by civil penalties not to exceed $27,500 per day.

Impact

ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable.

Background

On December 8, 1999, Phase II rules were published in the Federal Register requiring Napa County and the City of Napa to obtain an National Pollutant Discharge Elimination System (NPDES) permit for municipal stormwater discharges by March 10, 2003.  Subsequently, the San Francisco Regional Water Quality Control Board (RWQCB) added Yountville, St. Helena and Calistoga to the list of Phase II agencies required to obtain the permit.  The City of American Canyon was not initially included in the Phase II regulations because it was issued a Phase I permit in 2000, but the City was granted Phase II status by the RWQCB in 2005.

As required by the Phase II General Permit, a Stormwater Management Program (SWMP) was developed and submitted to the RWQCB on March 10, 2003.  The SWMP consists of Local Programs implemented by the County and the cities and a County-wide Program implemented by the Flood Control and Water Conservation District (District).  The District provides $30,000 from its Maintenance and Watershed Programs Project No. 96-1 fund to cover part of the County-wide Program costs.  The remainder of the County-wide program costs are paid for by the Napa County Stormwater Management Program (NCSWMP) co-permittees according to a cost-share formula based on fifty percent (50%) assessed on population size and fifty percent (50%) assessed on Benefit Assessment Units (BAUs).  BAUs are based upon land use and impervious surface area and are use by the District for the purpose of determining property assessments to fund the Watershed Maintenance Program.  The City of American Canyon contributes an additional $2,400 because its citizens are not included in the District's Maintenance and Watershed Program assessment.

The Phase II General Permit and the current SWMP expired during the 2007/2008 fiscal year.  The State Water Resource Control Board is currently drafting a new General Permit which is expect to be issued in the Spring of 2009.  At this time a new SWMP will need to be submitted to the RWQCB for approval.  On March 20, 2008 the Public Works Directors from the cities and the County met with Flood Control District staff to discuss the need to develop a new SWMP and the areas where the SWMP needs to be strengthened.  In particular, the RWQCB has commented that public education and outreach efforts should be increased.  Based on this discussion, the County, cities, and the Flood Control District agreed that staffing for the County-wide Program should  be increased from 0.6 Full Time Equivalent (FTE) to 1.0 FTE.  Amendment No.4 will increase the total budget for the County-wide Program from $128,400 to $148,400 and the County's cost share will increase from $28,475 to $34,408.

 

Attachments

There are no attachments to this item