"Spring Mountain Road Viaduct" RDS 07-17 - Approval of additional emergency work
Special Instruction
4/5 vote required
Recommendation
Director of Public Works acting as County Roads Commissioner requests the following actions regarding the "Spring Mountain Road Viaduct Project," RDS 07-17:
Finding of Emergency pursuant to Public Contact Code 1102 (4/5 vote required);
Finding of cost of needed repairs exceeding $25,000; and
Authorize the Roads Commissioner to have work done pursuant to Public Contract Code 20395(e).
Summary
While constructing the "Spring Mountain Road Viaduct," RDS 07-17, the contractor encountered poor soil conditions. Shoring for construction has failed, creating unsafe conditions. Alternate shoring must be installed to safeguard life and safety of workers, as well as motorists.
A supplemental contract is needed to compensate for unforeseen conditions. In order to comply with the construction deadline imposed by Federal Emergency Management Agency (FEMA) and to complete before the onset of heavy rains, approval for the construction contract is necessary to complete the project.
PRECEDURAL REQUIREMENTS:
Staff reports.
Public comments.
Motion, second, discussion and vote on the item.
Fiscal Impact
Is there a Fiscal Impact?
Yes
Is it Currently Budgeted?
Yes
Is the activity Mandatory or Discretionary
Mandatory
Is the General Fund Affected
No
Future Fiscal Impact?
All construction costs are expected to occur this Fiscal Year. While the project is funded through the Roads Department, FEMA reimbursement is expected.
Consequences if not approved
The viaduct repair cannot be constructed. Loss of the road and total road closure is possible, compromising public safety.
Additional Information
The scope and costs of the supplemental contract are unknown at the time of writing of this item and will be presented by staff report today.
Impact
ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations 15378 (State CEQA Guidelines) and therefore CEQA is not applicable..
Background
On July 22, 2008 the Board awarded the contract "Spring Mountain Road Viaduct," RDS 07-17, to Syblon Reid of Folsom, California in the amount of $599,860. Unforeseen soil conditions have led to unstable shoring, which must be addressed to provide safe working conditions to restore the integral ground of the roadway. The scope and costs of the supplemental contract are unknown at the time of writing of this item and will be presented by staff report today.
The Director of Public Works acting as County Roads Commissioner, appointed pursuant to Section 2006 of the Streets and Highways Code, requests:
The Board find that the situation is an emergency pursuant to Public Contract Code 1102, which states that 'Emergency'...means a sudden, unexpected occurrence that poses a clear and imminent danger, requiring immediate action to prevent or mitigate the loss or impairment of life, health, property, or essential public services;
The Board find the cost of the mitigation will be in excess of $25,000, as substantiated in the staff presentation today;
The Board authorize the Road Commissioner have the work done under his supervision pursuant to Public Contract Code 20395(e).
For emergency work, Public Contract Code Section 20395(e) allows for letting a contract covering work and materials without soliciting bids when the estimated cost exceeds $25,000 and the public interest and necessity demand immediate action to safeguard life, health, or property. The Code authorizes the Roads Commissioner to sign the contract needed to make such repairs.